7312
Comment:
|
8840
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 54: | Line 54: |
2017/1/29(Mon.) | 2017/2/15(Thur.) |
Line 59: | Line 59: |
* ETMY: *Enomomoto * IP damping was established. Loop of LVDT to LVDT including DC works well. * Optimum of point IP can be moved. Needs check again. |
|
Line 60: | Line 63: |
* Alignment * Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百mrad)でドリフトがあるもようだが、範囲は狭まって来ている。 |
* Alignment: *Izumi * Beam pointing to ETMY and BS was confirmed. * ETMY oplev moved more than 180urad, the reasons is not clear. * Somebody could hit the table of optical table. * Spot of ETMY by Tcam showed oplev spot moved a little. * Spot of "3" shape seems to be a reflection of something close. * Green: *Michimura, Yokogawa, Sugimoto * Green has been aligned to ETMY. * Beam is hitting at PR2 with 10cm off from center. * WAB: * Akutsu, Miyo, Simon * Making Photo sensors. One of the sensor was connected to ADC. * Door will be closed in the week of 3/5. * Sensors will be left after cooling. |
Line 64: | Line 82: |
* Vacuum: leak check * Alignment: Oplevのセンタリング。 |
* CAL: *Inoue, Yokozawa, Haino * IYA will be opened to complete Tcam. |
Line 67: | Line 85: |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
|
Line 68: | Line 89: |
* Laser hazard: Upstream of IMMT line | * Laser hazard: SR2-3. |
Line 71: | Line 92: |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
|
Line 72: | Line 98: |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
Line 76: | Line 102: |
* Week of 2/5 * 2/5 Cooling start. |
* Week of 2/26 * Beam alignment to REFL port. |
Line 79: | Line 105: |
* week of 3/5 * IYC door will be closed. |
|
Line 81: | Line 109: |
* Network cableの整理 * ピコモーターの反応がなくなる。 |
|
Line 94: | Line 121: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/15(Thur.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- IP damping was established. Loop of LVDT to LVDT including DC works well.
- Optimum of point IP can be moved. Needs check again.
- ETMY: *Enomomoto
- Alignment: *Izumi
- Beam pointing to ETMY and BS was confirmed.
- ETMY oplev moved more than 180urad, the reasons is not clear.
- Somebody could hit the table of optical table.
- Spot of ETMY by Tcam showed oplev spot moved a little.
- Spot of "3" shape seems to be a reflection of something close.
- ETMY oplev moved more than 180urad, the reasons is not clear.
- Beam pointing to ETMY and BS was confirmed.
- Green: *Michimura, Yokogawa, Sugimoto
- Green has been aligned to ETMY.
- Beam is hitting at PR2 with 10cm off from center.
- WAB: * Akutsu, Miyo, Simon
- Making Photo sensors. One of the sensor was connected to ADC.
- Door will be closed in the week of 3/5.
- Sensors will be left after cooling.
- Green has been aligned to ETMY.
- Work plan (*:responsible person)
- CAL: *Inoue, Yokozawa, Haino
- IYA will be opened to complete Tcam.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Inoue, Yokozawa, Haino
- Laser hazard: SR2-3.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Green setup.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- Week of 2/13
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)