Differences between revisions 276 and 296 (spanning 20 versions)
Revision 276 as of 2018-01-30 13:02:15
Size: 7573
Comment:
Revision 296 as of 2018-02-13 09:08:46
Size: 7737
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/30 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 54: Line 54:
2017/1/30(Tue.) 2017/2/13(Tue.)
Line 56: Line 56:
 * Remote participants by eZuce: Miyoki  * Remote participants by eZuce: Miyoki, Izumi
Line 59: Line 59:
  * Alignment: *Miyakawa
   * Temperature of mirror is now 230K, changed 40K from last Friday. Drift by cooling is quite small.
Line 60: Line 62:
  * Alignment
   * 数時間単位の線形レンジを振り切るような数100uradの大きな振動がある。Excitationが以前収まらない。

  * WAB: 目視でダンプの確認。
Line 66: Line 64:
  * Vacuum: leak check
  * WAB: Opleveのチェック
Line 69: Line 65:
 * Laser hazard: PSL area  * Laser hazard: IMM in the morning, SR2-3 in the afternoon.
Line 72: Line 68:

  * Week of 1/29
   * 1/29,30 leak check.
   * 1/30 Opening ETMY gate valve.
   * 1/30-2/2 Re-checking main beam to ETMY

  * Week of 2/5
   * 2/5 Cooling start.
  * Week of 2/13
    * Waiting for cooling the mirror.
Line 83: Line 73:
  * Network cableの整理
  * ETMYのピコモーターの反応がなくなる。
Line 96: Line 85:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/13(Tue.)

  • Remote participants by eZuce: Miyoki, Izumi
  • Report of work (*:responsible person)
    • Alignment: *Miyakawa
      • Temperature of mirror is now 230K, changed 40K from last Friday. Drift by cooling is quite small.
  • Work plan (*:responsible person)
  • Laser hazard: IMM in the morning, SR2-3 in the afternoon.
  • Weekly
    • Week of 2/13
      • Waiting for cooling the mirror.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)