Line 11: Line 11:
2017/1/30 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 54: Line 54:
2017/2/1(Thur.) 2017/2/19(Mon.)
Line 57: Line 57:
  * Recovery from the power outage in the morning.
Line 59: Line 60:
  * Vacuum: *木村、上田、宍戸、高橋
   * Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。
   * EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず。
    * 2mm下がって、0.5mm戻したような状態。しばらくは現状のまますすめて。来週もう一度トライする予定。
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
Line 64: Line 64:
  * Alignment: 和泉、桐井、道村、奥富
   * Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。
    * LVDTのDACにオフセットを加えると現れる。
   * エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。
    * BSにも光は返ってきた。
    * BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 71: Line 67:
  * 機器制御のチェック: *麻生、日立造船
   * センター、各エンド64chが使えるようになった。
 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.
Line 76: Line 71:
  * Vacuum: *和泉、早河
   * ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
  * CAL: *Haino
   * To check the safety of laser.
Line 79: Line 74:
  * IOO: *苔山
   * 今日一日光を使う。
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
Line 82: Line 78:
  * Alignment: *和泉
   * 午後にOplevの再センタリングをしたい。WABと時間調整。

  * WAB: *阿久津
   * 作業と重なるのでビームをできるだけ避けてほしい。アラインメントと時間調整。

  * Type B
   * Blade inspection.
   * Re-centering oplev.

 * Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。
 * Laser hazard: Upstream SR2-3 line.
Line 95: Line 81:
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 96: Line 85:
  * Week of 1/29
   * 1/31-2/2 Re-checking main beam to ETMY
  * Week of 2/26
   * Beam alignment to REFL port.
Line 99: Line 88:
  * Week of 2/5
   * 2/5 Cooling start.
  * week of 3/5
   * IYC door will be closed.
Line 102: Line 91:
  * week of 3/12
   * Connecting ducts at corner.
Line 104: Line 95:
  * Network cableの整理
  * EYVのピストンのリリースで防振系がフリーにはならない。
  * Leakが二箇所残っている。
Line 118: Line 107:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/19(Mon.)

  • Remote participants by eZuce: None
    • Recovery from the power outage in the morning.
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.

Glitch is still there but even if measurement with no glitch time has still no coherence.

  • PR RT models will be modified for Watch dog bug or something.
  • Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
  • Watch dog bug report: *Mark
    • Or stage was implemented instead of And stage at the watch dog part.
  • Work plan (*:responsible person)
    • CAL: *Haino
      • To check the safety of laser.
    • ETMY: Enomomoto, Izumi
      • Oplev will be centered and beam will be checked again.
      • PR2 will be lowered by ~3mm.
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents