Line 56: Line 56:
 * Remote participants by eZuce: Miyoki, Izumi  * Remote participants by eZuce: None
  * Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
Line 59: Line 60:
  * Alignment: *Miyakawa
   * Temperature of mirror is now 230K, changed 40K from last Friday. Drift by cooling is quite small.
  * ETMY: *Enomomoto
   * Calibration at cryopayload was performed.
  * Cryo: mirror temperature: 220K.
  * Green reached ETMY
   * PR2 had 500urad misalignment.
Line 64: Line 69:
  * ETMY: Enomomoto, Izumi
   * Returning IR light will be checked around BS.
   * Leveler wil be removed in the more

  * Green reached ETMY
   * PR2 had 500urad misalignment.
Line 69: Line 81:
  * Waiting for cooling the mirror.    * Waiting for cooling the mirror.
   * ETMY tuninng.
Line 71: Line 84:
  * Week of 2/19
   * ETMY tuninng.

  * Week of 2/26
   * Beam alignment to REFL port.
Line 73: Line 91:
  * AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
  * DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/13(Tue.)

  • Remote participants by eZuce: None
    • Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
  • Report of work (*:responsible person)
    • ETMY: *Enomomoto
      • Calibration at cryopayload was performed.
    • Cryo: mirror temperature: 220K.
    • Green reached ETMY
      • PR2 had 500urad misalignment.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Returning IR light will be checked around BS.
      • Leveler wil be removed in the more
    • Green reached ETMY
      • PR2 had 500urad misalignment.
  • Laser hazard: IMM in the morning, SR2-3 in the afternoon.
  • Weekly
    • Week of 2/13
      • Waiting for cooling the mirror.
      • ETMY tuninng.
    • Week of 2/19
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
  • Issues
    • AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
    • DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.

KAGRA/Commissioning/DailyWork
<< <  2024 / 4 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30          


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members