Differences between revisions 299 and 301 (spanning 2 versions)
Revision 299 as of 2018-02-14 09:31:45
Size: 8545
Comment:
Revision 301 as of 2018-02-16 09:28:12
Size: 8883
Comment:
Deletions are marked like this. Additions are marked like this.
Line 54: Line 54:
2017/2/14(Wed.) 2017/2/16(Fri.)
Line 56: Line 56:
 * Remote participants by eZuce: None
  * Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
 * Remote participants by eZuce: Yokozawa
  * Preparation of power outage at outside buildings on Sunday.
  * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
  * Keep control room clean!
Line 60: Line 62:
  * ETMY: *Enomomoto
   * Calibration at cryopayload was performed.
  * Cryo: mirror temperature: 220K.
  * Green reached ETMY
   * PR2 had 500urad misalignment.
  * Alignment and ETMY: *Izumi, Enomomoto
   * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
Line 66: Line 65:
 * Green: *Michimura, Yokogawa, Sugimoto
  * Green hits ETMY and IR hits both ends.
  * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
Line 67: Line 69:
 * Tcam:
  * Modifying some mechanical parts at KEK.

 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.

 * PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
Line 69: Line 78:
  * CAL: *Haino
   * To check the safety of laser.
Line 70: Line 82:
   * Returning IR light will be checked around BS.
   * Leveler wil be removed in the more
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
Line 73: Line 85:
  * Green reached ETMY
   * PR2 had 500urad misalignment.


 * Laser hazard: IMM in the morning, SR2-3 in the afternoon.
 * Laser hazard: Upstream SR2-3 line.
Line 83: Line 91:
   * Green setup.
Line 92: Line 101:
  * week of 3/5
   * IYC door will be closed.

  * week of 3/12
   * Vacuum at corner are will be performed in the week.
Line 93: Line 108:
  * AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
  * DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/16(Fri.)

  • Remote participants by eZuce: Yokozawa
    • Preparation of power outage at outside buildings on Sunday.
    • Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
    • Keep control room clean!
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
  • Green: *Michimura, Yokogawa, Sugimoto
    • Green hits ETMY and IR hits both ends.
    • Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
  • Tcam:
    • Modifying some mechanical parts at KEK.
  • Watch dog bug report: *Mark
    • Or stage was implemented instead of And stage at the watch dog part.
  • PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
  • Work plan (*:responsible person)
    • CAL: *Haino
      • To check the safety of laser.
    • ETMY: Enomomoto, Izumi
      • Oplev will be centered and beam will be checked again.
      • PR2 will be lowered by ~3mm.
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/13
      • Waiting for cooling the mirror.
      • ETMY tuninng.
      • Green setup.
      • 2/16 Preparation for power down.
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Vacuum at corner are will be performed in the week.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 5 >  >>
Mon Tue Wed Thu Fri Sat Sun
    1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31    


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)