Differences between revisions 84 and 313 (spanning 229 versions)
Revision 84 as of 2017-10-26 09:14:00
Size: 4206
Comment:
Revision 313 as of 2018-02-23 09:16:23
Size: 9215
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}


-----
Line 4: Line 17:
 * MIF + VIS  * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 6: Line 22:
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
  .
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==
Line 9: Line 27:
 . * 責任者  * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
Line 11: Line 41:

<<Anchor(Meetings)>>
Line 15: Line 47:
<<Anchor(MorningMeetings)>>
Line 18: Line 51:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 21: Line 54:
2017/10/26(Thu) 2017/2/23(Fri.)
Line 23: Line 56:
 * Daily
  * 作業人員(*:責任者)
   * MIF+VIS: *和泉、中野、井上、Mark、Fabian、Enzo、平田 (PHS: Mark、KEK-2(井上)、 V-3(和泉)、V-7(中野))
 * Remote participants by eZuce: None
Line 27: Line 58:
  * Laser hazard
   * PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 33: Line 63:
  * 作業
   * 計算機
    * k1pr0が復帰。現在はPR3のみ動かすようにしている。PRMの復帰はアラインメントが終わってから。
    * XYendの時間ずれが残っているので、今日の午前中に直す。
    * k1cam0が立ち上がっていない様子。
   * アラインメント
    * PSLの入射光のアラインメントのズレを直した。MCはそのまま。入射光のアラインメントを見るのにQPDをインストールした。
    * PR3のBFのダンピングのゲインが30倍良くなっていた。
    * Xエンドまで再び光が通った。直接光だと思われる。
    * 今日はBSも動かす予定。基本的には準備はできているはず。
   * X/Y end
  * Camera: Inoue, Haino, Yokozawa, Cory, Binhua
   * ETMY Camera is still under debugging. Camera seems to be broken.
   * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa, kokeyama
   * Making guardian script for ISS.


 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.

  * ISS: Koseyama, Kitazawa
   * Making RT models.


 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 46: Line 81:
  * 10/23の週: Yエンドに光を送る。   * Week of 2/19
   * ETMY tuninng.
Line 48: Line 84:
 * 問題点など
  * コーチフィルターが不調。
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.


 * Issues
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 55: Line 109:
<<Anchor(WeeklyMeetings)>>
Line 57: Line 112:
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/
6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||1
4||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/1
4||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]||
||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 69: Line 137:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
Line 70: Line 143:
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 78: Line 152:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/19 updated KAGRA/Commissioning/Commissioning_schedule_20180220.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/23(Fri.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
      • Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
      • It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
    • Camera: Inoue, Haino, Yokozawa, Cory, Binhua
      • ETMY Camera is still under debugging. Camera seems to be broken.
      • ITMY camera was aligned, and needs focus next.
    • IOO: Kitazawa, kokeyama
      • Making guardian script for ISS.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Diagonalizing matrix to close loop of marionette.
    • ISS: Koseyama, Kitazawa
      • Making RT models.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/19
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
      • 2/28: Height change for PRs
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues
    • The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
    • DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)