Differences between revisions 1 and 352 (spanning 351 versions)
Revision 1 as of 2017-10-03 12:10:54
Size: 167
Comment:
Revision 352 as of 2018-03-20 10:41:12
Size: 9826
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
-----
Line 3: Line 4:
 * [[KAGRA/Commissioning/Meeting|Meeting]] == Task list ==
Line 5: Line 6:
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}


-----
== Working people assignment ==
 * *: responsible person
  
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
-----
== Meetings ==

----
<<Anchor(MorningMeetings)>>
=== Morning meeting ===

 * Date and time: Every weekday, 9AM
 * Location: Control room, or eZuce


2017/3/20(Tue.)

 * Remote participants by eZuce: None

==== Report of work (*:responsible person) ====

 * VAC: *Uchiyama, Kimura, Suzuki
  * PR2 assembly frames will be removed soon.

 * Alignment: *Izumi
  * All alignment to REFL after pump down was verified.
   * Only ETMY was off position by ~100urad.

 * ETMY: *Miyamoto
  * Diagonal of sensors. Still going on.

 * BS: Eleonora, Izumi
  * Coil balance is going on.

 * IMC:
  * "sleep" commands were removed from Guardian.

 * Cal: Yokozawa
  * We checked all the IMC TFs.



==== Work plan (*:responsible person) ====

 * Alignment, ETMY: *Izumi

 * Cal: Yokozawa
  * Injection will be tested soon.


==== Laser hazard ====
 * [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
 * [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
 * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.

==== Weekly ====

 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa

 * week of 3/26
  * Rough alignment of ETMX will be planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.

 * Issues


<<MonthCalendar(KAGRA/Commissioning/DailyWork)>>


----
<<Anchor(WeeklyMeetings)>>
=== Weekly meeting ===
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]


-----
== Documents ==
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]

== Communication tools ==

   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)



------
Line 6: Line 171:
 * [[KAGRA/Commissioning/ML|Joining commissioning mailing list]]  * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]]

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/20(Tue.)

  • Remote participants by eZuce: None

Report of work (*:responsible person)

  • VAC: *Uchiyama, Kimura, Suzuki
    • PR2 assembly frames will be removed soon.
  • Alignment: *Izumi
    • All alignment to REFL after pump down was verified.
      • Only ETMY was off position by ~100urad.
  • ETMY: *Miyamoto
    • Diagonal of sensors. Still going on.
  • BS: Eleonora, Izumi
    • Coil balance is going on.
  • IMC:
    • "sleep" commands were removed from Guardian.
  • Cal: Yokozawa
    • We checked all the IMC TFs.

Work plan (*:responsible person)

  • Alignment, ETMY: *Izumi
  • Cal: Yokozawa
    • Injection will be tested soon.

Laser hazard

  • [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
  • [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
  • [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX will be planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 5 >  >>
Mon Tue Wed Thu Fri Sat Sun
    1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31    


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)