Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 * BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Enomoto |
Line 62: | Line 54: |
2017/12/19(Tue.) | 2017/2/26(Mon.) |
Line 64: | Line 56: |
* 作業報告 (*:責任者) * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本 * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。 * Fishing rodのスタックも直した。 |
* Remote participants by eZuce: Miyoki |
Line 69: | Line 58: |
* Vierport: *横澤、井上 * EYAにViewport設置完了。 |
* Report of work (*:responsible person) * Alignment and ETMY: *Enomoto * Photo sensor noise was improved on Thursday and checked on Friday. We confirmed the noise becomes better. * Sampling model of RT model was changed from 16kHz to 2kHz to reduce 10min period glitch. |
Line 72: | Line 63: |
* IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * コイルドライバーがおかしい可能性がある。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。 |
* Camera: Inoue, Haino, Yokozawa, Cory, Binhua * ETMY Camera was broken by taking too many photos. Camera will be replaced. * ITMY camera is being set to look at BS. * BS PD will be replaced by Yokozawa. |
Line 78: | Line 68: |
* 作業予定 (*:責任者) * アラインメント: *和泉 * 今日の昼休み12時から1時の間にスリットを置く。 |
* IOO: Kitazawa, kokeyama * IO chassis will be replaced and being prepared. |
Line 82: | Line 71: |
* Type A(ETMY): *高橋、牛場、都丸、和泉 * Fishing rodが動くか確認。 * IOO * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。 * MCの調子が悪い。 |
* CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
Line 90: | Line 75: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
|
Line 91: | Line 80: |
* Laser hazard * センターはSR奥がハザードエリア。 * 午後からYend 1Fがハザートエリアになる。 |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 96: | Line 83: |
* Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
|
Line 97: | Line 88: |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 * ETMYのアラインメント |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 103: | Line 101: |
* 問題点など * 回路電源のモニターがあるといい。 * MCの調子が悪い。 * IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 |
* Issues * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
Line 121: | Line 114: |
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 129: | Line 130: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 136: | Line 137: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/19 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/26(Mon.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Alignment and ETMY: *Enomoto
- Photo sensor noise was improved on Thursday and checked on Friday. We confirmed the noise becomes better.
- Sampling model of RT model was changed from 16kHz to 2kHz to reduce 10min period glitch.
- Camera: Inoue, Haino, Yokozawa, Cory, Binhua
- ETMY Camera was broken by taking too many photos. Camera will be replaced.
- ITMY camera is being set to look at BS.
- BS PD will be replaced by Yokozawa.
- IOO: Kitazawa, kokeyama
- IO chassis will be replaced and being prepared.
- CRY: mirror temperature ~110K.
- The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified.
- Alignment and ETMY: *Enomoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Ushiba
- Check the glitch with the 2kHz model.
- Original REFL port will be tested to pick up Mich signal.
- ETMY: Enomomoto, Ushiba
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- 2/28: Height change for PRs
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
- DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)