Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
Line 17: | Line 17: |
* *:responsible person * Re alignment * 1/11 *Izumi * 1/12 *Izumi |
* *: responsible person |
Line 22: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Enomoto |
Line 61: | Line 54: |
2017/1/10(Wed.) | 2017/3/6(Wed.) |
Line 63: | Line 56: |
* 12時半よりファン小屋で真空と低温の細かい打ち合わせ。 | * Remote participants by eZuce: Izumi |
Line 65: | Line 58: |
* Remote participants by educe: None | ==== Report of work (*:responsible person) ==== * Alignment: Enomoto, Izumi * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26. |
Line 67: | Line 62: |
* Report of work (*:responsible person) | * AOS: Akutsu, Michimura * We replace all the items which were not compatible to vacuum. |
Line 69: | Line 65: |
* Work plan (*:responsible person) | * Tcam: * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light. * CRY: mirror temperature 24K. ==== Work plan (*:responsible person) ==== * Alignment: Enomoto * PD at BS will be moved to REFL. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. * AOS: Akutsu, Michimura * Alignment of green light to ETMY will be finished today. ==== Laser hazard ==== * AM: Around PR2 for green, Y-end for IR. * PM: Around PR2 for green, upstream SR2-3 line for IR. |
Line 72: | Line 84: |
* Laser hazard * センターはIMM奥がハザードエリア。 |
==== Weekly ==== * week of 3/5 * 3/5 Exchanging items and cleaning inside the PR2 chamber * 3/8 IYC door will be closed. |
Line 75: | Line 89: |
* Weekly * Week of 1/8 * vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
Line 81: | Line 93: |
* Week of 1/15 * IOO works. * Pump down, leak check in the later of this week. |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
Line 86: | Line 100: |
Line 93: | Line 106: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 98: | Line 111: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 108: | Line 128: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 115: | Line 135: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/6(Wed.)
- Remote participants by eZuce: Izumi
Report of work (*:responsible person)
- Alignment: Enomoto, Izumi
- Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
- AOS: Akutsu, Michimura
- We replace all the items which were not compatible to vacuum.
- Tcam:
- Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
- CRY: mirror temperature 24K.
Work plan (*:responsible person)
- Alignment: Enomoto
- PD at BS will be moved to REFL.
- Connection of PD signal to DAQ should be implemented this week or next week.
- GigE camera should be placed at the REFL port eventually.
- AOS: Akutsu, Michimura
- Alignment of green light to ETMY will be finished today.
Laser hazard
- AM: Around PR2 for green, Y-end for IR.
- PM: Around PR2 for green, upstream SR2-3 line for IR.
Weekly
- week of 3/5
- 3/5 Exchanging items and cleaning inside the PR2 chamber
- 3/8 IYC door will be closed.
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools