Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/11 *Izumi * 1/12 *Izumi |
|
Line 22: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Enomoto |
Line 61: | Line 54: |
2017/1/11(Thrs.) | 2017/2/28(Wed.) |
Line 63: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Izumi |
Line 66: | Line 59: |
* Alignment and ETMY: *Enomoto, Ushiba, Miyamoto * Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm. * Damping of pitch is still under investigation. TFs of pitch role etc. are dirty. * IOO: kokeyama * A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one. * It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis. * CRY: mirror temperature ~100K. |
|
Line 68: | Line 72: |
* Alignment: *Izumi * Oplev, Re-alignment |
|
Line 71: | Line 73: |
* Check of PLC at Yend for connection to measurement tools: Aso | * Camera: Yokozawa * BS figure will be checked if no laser was coming. |
Line 73: | Line 76: |
* Marionet Oplev: Akutsu * Laser hazard area * Behind of BS and SR line and Yend 1F |
* Height change of PRs: * Height of PR2 and PR2 will be lowered today. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 79: | Line 82: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
* Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
Line 83: | Line 87: |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
Line 87: | Line 91: |
* Week of 1/22 * 1/24,25 leak check. |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
Line 90: | Line 95: |
* Week of 1/29 * 1/29 Cooling start |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 94: | Line 101: |
Line 106: | Line 112: |
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 116: | Line 128: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 123: | Line 135: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/26 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/28(Wed.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
- Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm.
- Damping of pitch is still under investigation. TFs of pitch role etc. are dirty.
- IOO: kokeyama
- A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one.
- It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis.
- CRY: mirror temperature ~100K.
- Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
- Work plan (*:responsible person)
- Camera: Yokozawa
- BS figure will be checked if no laser was coming.
- Height change of PRs:
- Height of PR2 and PR2 will be lowered today.
- Camera: Yokozawa
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- 2/28: Height change for PRs
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)