Line 11: Line 11:
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi
Line 21: Line 19:
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
 * Beam leading to REFP port
  * *Enomoto
Line 60: Line 54:
2017/1/12(Fri.) 2017/3/6(Wed.)
Line 62: Line 56:
 * Remote participants by educe: None  * Remote participants by eZuce: Izumi
Line 64: Line 58:
 * Affect of short power failure
  * VIS
   * EX のポラリティーが反転していた。瞬停と関係あるかは不明。
=== Report of work (*:responsible person) ===
 * Alignment: Enomoto, Izumi
  * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
Line 68: Line 62:
  * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
   * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
 * AOS: Akutsu, Michimura
  * We replace all the items which were not compatible to vacuum.
Line 71: Line 65:
  * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.  * Tcam:
  * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
Line 73: Line 68:
 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * X-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
    * GASは真空槽を開けずに直せる範囲を超えている模様。
    * PR3で100uradのオーダーでずれていた。
    * Oplevの範囲内には入っているが、PRの曲率によりゼロ点意味をなさなくなっている。
 * CRY: mirror temperature 24K.

=== Work plan (*:responsible person) ===
 * Alignment: Enomoto
  * PD at BS will be moved to REFL.
  * Connection of PD signal to DAQ should be implemented this week or next week.
  * GigE camera should be placed at the REFL port eventually.

 * AOS: Akutsu, Michimura
  * Alignment of green light to ETMY will be finished today.

=== Laser hazard ===
 * AM: Around PR2 for green, Y-end for IR.
 * PM: Around PR2 for green, upstream SR2-3 line for IR.
Line 82: Line 84:
  * PLC at Yend: Aso
   * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。
=== Weekly ===
 * week of 3/5
  * 3/5 Exchanging items and cleaning inside the PR2 chamber
  * 3/8 IYC door will be closed.
Line 85: Line 89:
  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
 * week of 3/12
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.

 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
Line 89: Line 99:
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。

  * Marionet Oplev: Akutsu
   * QPDの信号を確認する予定。

 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F

 * Weekly
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.

  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start
Line 116: Line 100:
   * EX のポラリティーが反転していた。回路の問題か?
   * 真空曹を開けてPR2とPR3を直すかどうか。
Line 129: Line 111:
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 139: Line 128:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 146: Line 135:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/5 updated KAGRA/Commissioning/Commissioning_schedule_20180306.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Enomoto



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/6(Wed.)

  • Remote participants by eZuce: Izumi

Report of work (*:responsible person)

  • Alignment: Enomoto, Izumi
    • Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
  • AOS: Akutsu, Michimura
    • We replace all the items which were not compatible to vacuum.
  • Tcam:
    • Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
  • CRY: mirror temperature 24K.

Work plan (*:responsible person)

  • Alignment: Enomoto
    • PD at BS will be moved to REFL.
    • Connection of PD signal to DAQ should be implemented this week or next week.
    • GigE camera should be placed at the REFL port eventually.
  • AOS: Akutsu, Michimura
    • Alignment of green light to ETMY will be finished today.

Laser hazard

  • AM: Around PR2 for green, Y-end for IR.
  • PM: Around PR2 for green, upstream SR2-3 line for IR.

Weekly

  • week of 3/5
    • 3/5 Exchanging items and cleaning inside the PR2 chamber
    • 3/8 IYC door will be closed.
  • week of 3/12
    • TMS installation at ETMY.
    • Connecting ducts at the corner area.
  • week of 3/19
    • Vacuum test at at the corner area.
    • TMS alignment using green light at ETMY.
    • Beam alignment to REFL port.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

20

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1