Line 11: Line 11:
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi
Line 21: Line 19:
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
 * Beam leading to REFP port
  * *Enomoto
Line 60: Line 54:
2017/1/15(Mon.) 2017/3/1(Thur.)
Line 62: Line 56:
 * Remote participants by educe: None  * Remote participants by eZuce: None
Line 65: Line 59:
  * Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo
   * ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。
   * BSのLを押してPが出ないようにする。DCはうまくいったが高周波がまだ十分でない。
  * 干渉計ビームはX-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。直すのは延期。
Line 71: Line 60:
  * 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。   * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
Line 74: Line 70:
  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.

  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.


  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.

  * CRY: mirror temperature ~94K.
Line 79: Line 85:
  * Alignment: *Izumi
   * Buffule PDを入れるので、その回路を用意する。
Line 82: Line 86:
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。   * Alignment:
   * IMMT and MC will be aligned to center PRs.
Line 84: Line 89:
  * PLC at Yend: Aso
   * MEDMを作成している。
 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 91: Line 92:
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
  * Week of 2/26
   * ETMY tuninng.
  * Beam alignment to REFL port.
   * 2/28: Height change for PRs
Line 95: Line 97:
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
Line 99: Line 101:
  * Week of 1/22
   * 1/24,25 leak check.
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.
Line 102: Line 105:
  * Week of 1/29
   * 1/29 Cooling start
  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
Line 105: Line 109:
 * Laser hazard: to be changed to IMM line in the morning.
Line 119: Line 122:
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 129: Line 138:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 136: Line 145:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/26 updated KAGRA/Commissioning/Commissioning_schedule_20180227.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Enomoto



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/1(Thur.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
      • We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
      • PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
      • Fishing rods worked well and still were within the range.
      • LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
        • Recorded the current height and current value.
      • It means that the beam changed upstream PR like IMMT, or MC.
      • We absolutely need monitors to check beam position at all the mirrors.
    • IOO: kokeyama
      • A good IO chassis changed and everything seems to be OK now.
    • AOS:
      • Lasers of oplev will can be dying soon.
        • The lifetime is about 100000h.
    • Camara: Yokozawa, Inouse
      • We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.
    • CRY: mirror temperature ~94K.
  • Work plan (*:responsible person)
    • Alignment:
      • IMMT and MC will be aligned to center PRs.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/26
      • ETMY tuninng.
      • Beam alignment to REFL port.
      • 2/28: Height change for PRs
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)