7911
Comment:
|
8834
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Enomoto |
Line 60: | Line 54: |
2017/1/15(Mon.) | 2017/3/5(Mon.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Izumi |
Line 65: | Line 59: |
* Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo * ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。 * BSのLを押してPが出ないようにするフィルターを実装している。DCはうまくいったが高周波がまだ十分でない。 * 先週の時点で干渉計ビームはX-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。PR系を直すのは来週以降に延期。 |
|
Line 71: | Line 60: |
* 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。 | * Alignment: Enomoto, Miyo, Yokozawa * We found beam at the IYA but it is not clear PR or BS is misaligned. * IOO: * IMMT2 cannot be seen by camera. We will work on camera this week. * CRY: mirror temperature 71K. |
Line 74: | Line 69: |
* Alignment: *Izumi * Baffle PDを入れるので、その回路を用意する。 |
|
Line 77: | Line 70: |
* PLC at Yend: Aso * MEDMを作成している。 * Laser hazard: to be changed to IMM line in the morning. |
* Alignment: Enomoto * We will find beam at the ETMY or ETMX by dithering PR3. * BS: Mark * We lift up the optical table and change items to vacuum compatible one. It does not change BS alignment an oplev. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 83: | Line 80: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. |
* Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. |
Line 89: | Line 84: |
* Week of 1/22 * 1/24,25 leak check. |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
Line 92: | Line 88: |
* Week of 1/29 * 1/29 Cooling start |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 108: | Line 109: |
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 118: | Line 125: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 125: | Line 132: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/26 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/5(Mon.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment: Enomoto, Miyo, Yokozawa
- We found beam at the IYA but it is not clear PR or BS is misaligned.
- IOO:
- IMMT2 cannot be seen by camera. We will work on camera this week.
- CRY: mirror temperature 71K.
- Alignment: Enomoto, Miyo, Yokozawa
- Work plan (*:responsible person)
- Alignment: Enomoto
- We will find beam at the ETMY or ETMX by dithering PR3.
- BS: Mark
- We lift up the optical table and change items to vacuum compatible one. It does not change BS alignment an oplev.
- Alignment: Enomoto
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools