Line 11: | Line 11: |
2017/1/15 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Enomoto |
Line 60: | Line 54: |
2017/1/16(Tue.) | 2017/3/2(Fri.) |
Line 62: | Line 56: |
* Remote participants by educe: Inoue | * Remote participants by eZuce: None |
Line 65: | Line 59: |
* Alignment: *Izumi * Baffle PDを入れるので、その回路を用意している。Oplev回路を改造してつかう。 |
|
Line 68: | Line 60: |
* BS: 新井 * L2Pをフィルターを設計した。DCもそこそ、高周波もかなりいったが、すごく低い周波数はもう少し改良する必要がある。 |
* Alignment: Enomoto, Miyo, Yokozawa * IMC and IMMT was aligned to center PRs. * Beam spot was not seen at the end. * We absolutely need monitors to check beam position at all the mirrors. * IOO: kokeyama * Alignment to MC was fixe. * AOS: * Lasers of oplev will can be dying soon. * The lifetime is about 100000h. * CRY: mirror temperature 89K. |
Line 72: | Line 76: |
* Alignment: *Izumi * EYでものの準備など。 |
|
Line 75: | Line 77: |
* Laser hazard: Upstream of IMM line. | * Alignment: * Alignment to IYA, or IYC will be checked and we will find the spot at the end then. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 79: | Line 83: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. |
* Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. |
Line 85: | Line 87: |
* Week of 1/22 * 1/24,25 leak check. |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
Line 88: | Line 91: |
* Week of 1/29 * 1/29 Cooling start |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 104: | Line 112: |
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 114: | Line 128: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 121: | Line 135: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/26 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/2(Fri.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment: Enomoto, Miyo, Yokozawa
- IMC and IMMT was aligned to center PRs.
- Beam spot was not seen at the end.
- We absolutely need monitors to check beam position at all the mirrors.
- IOO: kokeyama
- Alignment to MC was fixe.
- AOS:
- Lasers of oplev will can be dying soon.
- The lifetime is about 100000h.
- Lasers of oplev will can be dying soon.
- CRY: mirror temperature 89K.
- Alignment: Enomoto, Miyo, Yokozawa
- Work plan (*:responsible person)
- Alignment:
- Alignment to IYA, or IYC will be checked and we will find the spot at the end then.
- Alignment:
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)