Line 11: Line 11:
2017/1/16 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/3/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi
Line 21: Line 19:
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
 * Beam leading to REFP port
  * *Enomoto
Line 60: Line 54:
2017/1/16(Tue.) 2017/3/6(Wed.)
Line 62: Line 56:
 * Remote participants by educe: Inoue  * Remote participants by eZuce: Izumi
Line 65: Line 59:
  * Alignment: *Izumi
   * Baffle PDを入れるので、その回路を用意している。Oplev回路を改造してつかう。
Line 68: Line 60:
  * BS: 新井
   * L2Pをフィルターを設計した。DCもそこそ、高周波もかなりいったが、すごく低い周波数はもう少し改良する必要がある。
  * Alignment: Enomoto, Izumi
   * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.

  * AOS: Akutsu, Michimura
   * We replace all the items which were not compatible to vacuum.

 * Tcam:
  * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.

  * CRY: mirror temperature 24K.
Line 72: Line 72:
  * Alignment: *Izumi
   * EYでものの準備など。
Line 75: Line 73:
   * Laser hazard: Upstream of IMM line.   * Alignment: Enomoto
   * PD at BS will be moved to REFL.
   * Connection of PD signal to DAQ should be implemented this week or next week.
   * GigE camera should be placed at the REFL port eventually.

  * AOS: Akutsu, Michimura
   * Alignment of green light to ETMY will be finished today.

 * Laser hazard:
  * AM: Around PR2 for green, Y-end for IR.
  * PM: Around PR2 for green, upstream SR2-3 line for IR.
Line 79: Line 87:
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.
  * week of 3/5
   * 3/5 Exchanging items and cleaning inside the PR2 chamber
   * 3/8 IYC door will be closed.
Line 85: Line 91:
  * Week of 1/22
   * 1/24,25 leak check.
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.
Line 88: Line 95:
  * Week of 1/29
   * 1/29 Cooling start
  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
   * Beam alignment to REFL port.
Line 104: Line 113:
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 114: Line 130:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 121: Line 137:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/5 updated KAGRA/Commissioning/Commissioning_schedule_20180306.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Enomoto



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/6(Wed.)

  • Remote participants by eZuce: Izumi
  • Report of work (*:responsible person)
    • Alignment: Enomoto, Izumi
      • Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
    • AOS: Akutsu, Michimura
      • We replace all the items which were not compatible to vacuum.
  • Tcam:
    • Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
    • CRY: mirror temperature 24K.
  • Work plan (*:responsible person)
    • Alignment: Enomoto
      • PD at BS will be moved to REFL.
      • Connection of PD signal to DAQ should be implemented this week or next week.
      • GigE camera should be placed at the REFL port eventually.
    • AOS: Akutsu, Michimura
      • Alignment of green light to ETMY will be finished today.
  • Laser hazard:
    • AM: Around PR2 for green, Y-end for IR.
    • PM: Around PR2 for green, upstream SR2-3 line for IR.
  • Weekly
    • week of 3/5
      • 3/5 Exchanging items and cleaning inside the PR2 chamber
      • 3/8 IYC door will be closed.
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
      • Beam alignment to REFL port.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

20

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)