8229
Comment:
|
9286
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/16 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/3/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180306.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Enomoto |
Line 60: | Line 54: |
2017/1/18(Thur.) | 2017/3/6(Wed.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Izumi |
Line 65: | Line 59: |
* Alignment: *Izumi * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。 * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。 * CryoPayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。 |
|
Line 70: | Line 60: |
* IOO * PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。 |
* Alignment: Enomoto, Izumi * Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26. * AOS: Akutsu, Michimura * We replace all the items which were not compatible to vacuum. * Tcam: * Tcam of ETMY was recovered. Team of ITMX can be seen in visible light. * CRY: mirror temperature 24K. |
Line 75: | Line 72: |
* Alignment: *Izumi * BSからETMYにビームを飛ばしたが、まだ見えていない。ゲインが500倍くらい低かったせい。午後3、4時頃から、再度ゲインを上げて試す。 * CryoPayloadのVisual inspection. * φ800フランジは今日は開けておく。明日しめる。 |
|
Line 80: | Line 73: |
* IOO * 1WをMCに入れる * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment. |
* Alignment: Enomoto * PD at BS will be moved to REFL. * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually. * AOS: Akutsu, Michimura * Alignment of green light to ETMY will be finished today. * Laser hazard: * AM: Around PR2 for green, Y-end for IR. * PM: Around PR2 for green, upstream SR2-3 line for IR. |
Line 86: | Line 87: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. |
* week of 3/5 * 3/5 Exchanging items and cleaning inside the PR2 chamber * 3/8 IYC door will be closed. |
Line 92: | Line 91: |
* Week of 1/22 * 1/24,25 leak check. |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
Line 95: | Line 95: |
* Week of 1/29 * 1/29 Cooling start |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
Line 100: | Line 102: |
* Network cableの整理 | |
Line 112: | Line 113: |
||20||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 122: | Line 130: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 129: | Line 137: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/6(Wed.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment: Enomoto, Izumi
- Beam has been lead to the REFL port. No need to vent after stopping the pump in the week of 3/26.
- AOS: Akutsu, Michimura
- We replace all the items which were not compatible to vacuum.
- Alignment: Enomoto, Izumi
- Tcam:
- Tcam of ETMY was recovered. Team of ITMX can be seen in visible light.
- CRY: mirror temperature 24K.
- Work plan (*:responsible person)
- Alignment: Enomoto
- PD at BS will be moved to REFL.
- Connection of PD signal to DAQ should be implemented this week or next week.
- GigE camera should be placed at the REFL port eventually.
- AOS: Akutsu, Michimura
- Alignment of green light to ETMY will be finished today.
- Alignment: Enomoto
- Laser hazard:
- AM: Around PR2 for green, Y-end for IR.
- PM: Around PR2 for green, upstream SR2-3 line for IR.
- Weekly
- week of 3/5
- 3/5 Exchanging items and cleaning inside the PR2 chamber
- 3/8 IYC door will be closed.
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- week of 3/5
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools