Line 11: | Line 11: |
2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
Line 19: | Line 19: |
* Pump down * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
|
Line 23: | Line 20: |
* *Izumi | * *Enomoto |
Line 57: | Line 54: |
2017/1/19(Thur.) | 2017/2/28(Wed.) |
Line 59: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Izumi |
Line 62: | Line 59: |
* Vacuum * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY. |
* Alignment and ETMY: *Enomoto, Ushiba, Miyamoto * Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm. * Damping of pitch is still under investigation. TFs of pitch role etc. are dirty. |
Line 65: | Line 63: |
* IOO: *Kokeyama * 1WがMCに入った。 |
|
Line 68: | Line 64: |
* Alignment: *Izumi * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。 * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。 * ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。 |
* IOO: kokeyama * A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one. * It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis. * CRY: mirror temperature ~100K. |
Line 74: | Line 72: |
* Alignment: *Izumi * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。 * 11時頃からレーザーハザードを全域に変更してアラインメント作業。 |
|
Line 78: | Line 73: |
* Camera: Yokozawa * BS figure will be checked if no laser was coming. |
|
Line 79: | Line 76: |
* 真空引きの最終判断は月曜日にする。 * チェックリスト最終確認。 * φ800フランジを閉める。 |
* Height change of PRs: * Height of PR2 and PR2 will be lowered today. |
Line 83: | Line 79: |
* Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM. | * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 87: | Line 82: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting |
* Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
Line 92: | Line 87: |
* Week of 1/22 * 1/23: Pump down. * 1/24: Turbo pump on. |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
Line 96: | Line 91: |
* Week of 1/29 * 1/29,30 leak check. |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
Line 99: | Line 95: |
* Week of 2/5 * Cooling start. |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 105: | Line 101: |
* Network cableの整理 | |
Line 117: | Line 112: |
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
|
Line 128: | Line 128: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/26 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/28(Wed.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
- Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm.
- Damping of pitch is still under investigation. TFs of pitch role etc. are dirty.
- IOO: kokeyama
- A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one.
- It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis.
- CRY: mirror temperature ~100K.
- Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
- Work plan (*:responsible person)
- Camera: Yokozawa
- BS figure will be checked if no laser was coming.
- Height change of PRs:
- Height of PR2 and PR2 will be lowered today.
- Camera: Yokozawa
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- 2/28: Height change for PRs
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)