Line 11: | Line 11: |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
Line 19: | Line 19: |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
|
Line 23: | Line 20: |
* *Izumi | * *Enomoto |
Line 57: | Line 54: |
2017/1/23(Tue.) | 2017/2/26(Mon.) |
Line 59: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Miyoki |
Line 62: | Line 59: |
* IOO: 苔山 * 精密空調が入って、温度が安定した。 |
* Alignment and ETMY: *Enomoto * Photo sensor noise was improved on Thursday and checked on Friday. We confirmed the noise becomes better. * Sampling model of RT model was changed from 16kHz to 2kHz to reduce 10min period glitch. |
Line 65: | Line 63: |
* Vacuum * Oplevがヒートリンクで遮られていた。 * Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。 * 再度戻り光も確認した。 * 真空引きの準備がほぼ完了。 |
* Camera: Inoue, Haino, Yokozawa, Cory, Binhua * ETMY Camera was broken by taking too many photos. Camera will be replaced. * ITMY camera is being set to look at BS. * BS PD will be replaced by Yokozawa. |
Line 71: | Line 68: |
* BS:神津、Enzo * リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。 |
* IOO: Kitazawa, kokeyama * IO chassis will be replaced and being prepared. * CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
Line 76: | Line 76: |
* Vacuum * 昨日午後から延期になって、本日朝真空引き予定 * ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川 * コントロールルーム: 和泉、奥富 * Check listによる最終確認 |
* ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
Line 82: | Line 80: |
* Laser hazard: 今日は午前はPSLのみ。午後からIMMT。 | * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 85: | Line 83: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
* Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
Line 89: | Line 88: |
* Week of 1/29 * 1/29,30 leak check. |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
Line 92: | Line 92: |
* Week of 2/5 * 2/5 Cooling start. |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 97: | Line 102: |
* Network cableの整理 * ピコモーターの反応がなくなる。 |
* DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
Line 110: | Line 114: |
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/26 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/26(Mon.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Alignment and ETMY: *Enomoto
- Photo sensor noise was improved on Thursday and checked on Friday. We confirmed the noise becomes better.
- Sampling model of RT model was changed from 16kHz to 2kHz to reduce 10min period glitch.
- Camera: Inoue, Haino, Yokozawa, Cory, Binhua
- ETMY Camera was broken by taking too many photos. Camera will be replaced.
- ITMY camera is being set to look at BS.
- BS PD will be replaced by Yokozawa.
- IOO: Kitazawa, kokeyama
- IO chassis will be replaced and being prepared.
- CRY: mirror temperature ~110K.
- The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified.
- Alignment and ETMY: *Enomoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Ushiba
- Check the glitch with the 2kHz model.
- Original REFL port will be tested to pick up Mich signal.
- ETMY: Enomomoto, Ushiba
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- 2/28: Height change for PRs
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
- DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)