Line 11: Line 11:
2017/1/23 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
Line 19: Line 19:
 * Pump down
  * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 23: Line 20:
  * *Izumi   * *Enomoto
Line 57: Line 54:
2017/1/26(Fri.) 2017/3/1(Thur.)
Line 59: Line 56:
 * Remote participants by eZuce:  * Remote participants by eZuce: None
Line 63: Line 60:
  * Vacuum
   * ターボポンプを入れた。
  * Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
   * We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
   * PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
   * Fishing rods worked well and still were within the range.
   * LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
    * Recorded the current height and current value.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
Line 66: Line 69:
  * Alignment
   * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。
   
  * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada
   * k1iy0への電源ケーブルの仕上げ。
   * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。

  * IOO: kokeyama
   * A good IO chassis changed and everything seems to be OK now.

  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.


  * Camara: Yokozawa, Inouse
   * We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.

  * CRY: mirror temperature ~94K.
Line 74: Line 85:
  * 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。
  * Alignment: Oplevのセンタリング。
Line 77: Line 86:
  * Alignment:
   * IMMT and MC will be aligned to center PRs.
Line 78: Line 89:
 * Laser hazard: Upstream of IMMT line  * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 81: Line 92:
  * Week of 1/22
   * 1/24: Pump down.
   * 1/25: Turbo pump on.
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
Line 85: Line 97:
  * Week of 1/29
   * 1/29,30 leak check.
   * 1/30 Opening ETMY gate valve.
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
Line 89: Line 101:
  * Week of 2/5
   * 2/5 Cooling start.
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
Line 94: Line 111:
  * Network cableの整理
  * ピコモーターの反応がなくなる。
Line 107: Line 122:
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/26 updated KAGRA/Commissioning/Commissioning_schedule_20180227.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Enomoto



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/1(Thur.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Height change of PRs: Tomaru, *Aso, Takahashi, Ohishi, Miyo
      • We opened the PR2 and PR3 chamber and we confirmed that the height of keystone and mirror of PR2 and PR3 were not at the wrong point.
      • PR2 was within ~1mm range and PR3 was ~5mm range from the center line. The height of RP3 was changed a bit by fishing rod, and we did not change PR2.
      • Fishing rods worked well and still were within the range.
      • LVDT seemed to have jumps several times in the past, so absolute position of LVDT is not trustable.
        • Recorded the current height and current value.
      • It means that the beam changed upstream PR like IMMT, or MC.
      • We absolutely need monitors to check beam position at all the mirrors.
    • IOO: kokeyama
      • A good IO chassis changed and everything seems to be OK now.
    • AOS:
      • Lasers of oplev will can be dying soon.
        • The lifetime is about 100000h.
    • Camara: Yokozawa, Inouse
      • We tried to see BS using Tcam at IXC, but we could not see the BS even with an illuminator. This may be because of the limit of area of viewport on the gate valve.
    • CRY: mirror temperature ~94K.
  • Work plan (*:responsible person)
    • Alignment:
      • IMMT and MC will be aligned to center PRs.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/26
      • ETMY tuninng.
      • Beam alignment to REFL port.
      • 2/28: Height change for PRs
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)