Line 11: | Line 11: |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
Line 20: | Line 20: |
* *Izumi | * *Enomoto |
Line 54: | Line 54: |
2017/1/29(Mon.) | 2017/2/27(Tue.) |
Line 56: | Line 56: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Izumi |
Line 59: | Line 59: |
* Alignment and ETMY: *Enomoto, Ushiba, Yamamoto * Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area. * Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared! |
|
Line 60: | Line 63: |
* Alignment * Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百mrad)でドリフトがあるもようだが、範囲は狭まって来ている。 |
* IOO: kokeyama * IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still. * CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
Line 64: | Line 71: |
* Vacuum: leak check * Alignment: Oplevのセンタリング。 |
* ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
Line 67: | Line 75: |
* Camera: Yokozawa * fine tuning and safety. |
|
Line 68: | Line 78: |
* Laser hazard: Upstream of IMMT line | * Height change of PRs: * It will be planed tomorrow. Preparation is almost done. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 71: | Line 84: |
* Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
|
Line 72: | Line 89: |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
Line 76: | Line 93: |
* Week of 2/5 * 2/5 Cooling start. |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 81: | Line 103: |
* Network cableの整理 * ピコモーターの反応がなくなる。 |
|
Line 94: | Line 114: |
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/26 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/27(Tue.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment and ETMY: *Enomoto, Ushiba, Yamamoto
- Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area.
- Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared!
- IOO: kokeyama
- IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still.
- CRY: mirror temperature ~110K.
- The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified.
- Alignment and ETMY: *Enomoto, Ushiba, Yamamoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Ushiba
- Check the glitch with the 2kHz model.
- Original REFL port will be tested to pick up Mich signal.
- ETMY: Enomomoto, Ushiba
- Camera: Yokozawa
- fine tuning and safety.
- Height change of PRs:
- It will be planed tomorrow. Preparation is almost done.
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- 2/28: Height change for PRs
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)