Line 11: | Line 11: |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 53: | Line 50: |
=== 2018/4/6(Fri.) === | |
Line 54: | Line 52: |
2017/2/16(Fri.) | * Remote participants by eZuce: Kimura, Miyoki, Yokozawa |
Line 56: | Line 54: |
* Remote participants by eZuce: Yokozawa * Preparation of power outage at outside buildings on Sunday. * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS. * Keep control room clean! |
==== Report of work (*:responsible person) ==== * IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto * Both light was confirmed at ETMX last night. * BS model was split, and no glitch was seen. Upper model is running at 4kHz and lower model is running at 16kHz. * Connection between k1lsc and k1bs is still something wrong. * Quality of ETMX looks much better than EMY. No bright spot was seen. |
Line 61: | Line 61: |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours. |
* ETMY: *Miyamoto * Covered on Oplev. |
Line 65: | Line 64: |
* Green: *Michimura, Yokogawa, Sugimoto * Green hits ETMY and IR hits both ends. * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen. |
|
Line 69: | Line 65: |
* Tcam: * Modifying some mechanical parts at KEK. |
==== Work plan (*:responsible person) ==== * Alignment: Izumi * No light is used in the daytime. Start using beam from evening. |
Line 72: | Line 69: |
* Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. |
* DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
Line 75: | Line 72: |
* PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next. | * Vacuum: *Kimura * Closing door will be performed in the next week as planned. |
Line 77: | Line 75: |
* Work plan (*:responsible person) * CAL: *Haino * To check the safety of laser. |
|
Line 81: | Line 76: |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 85: | Line 84: |
* Laser hazard: Upstream SR2-3 line. | * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 87: | Line 88: |
* Weekly * Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
|
Line 94: | Line 89: |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
==== Weekly ==== |
Line 98: | Line 91: |
* Week of 2/26 * Beam alignment to REFL port. |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
Line 101: | Line 96: |
* week of 3/5 * IYC door will be closed. |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
Line 104: | Line 100: |
* week of 3/12 * Vacuum at corner are will be performed in the week. |
==== Issues ==== |
Line 107: | Line 102: |
* Issues | |
Line 115: | Line 109: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 120: | Line 114: |
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || |
|
Line 141: | Line 142: |
* Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/6(Fri.)
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Report of work (*:responsible person)
- IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
- Both light was confirmed at ETMX last night.
- BS model was split, and no glitch was seen. Upper model is running at 4kHz and lower model is running at 16kHz.
- Connection between k1lsc and k1bs is still something wrong.
- Quality of ETMX looks much better than EMY. No bright spot was seen.
- ETMY: *Miyamoto
- Covered on Oplev.
Work plan (*:responsible person)
- Alignment: Izumi
- No light is used in the daytime. Start using beam from evening.
- DAQ: *Miyakawa
- Memory will be increased today. SSD might be tested today at k1tw0.
- Vacuum: *Kimura
- Closing door will be performed in the next week as planned.
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)