Line 11: Line 11:
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 53: Line 50:
=== 2018/4/16(Mon.) ===
Line 54: Line 52:
2017/2/16(Fri.) * Remote participants by eZuce: Miyoki
Line 56: Line 54:
 * Remote participants by eZuce: Yokozawa
  * Preparation of power outage at outside buildings on Sunday.
  * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
  * Keep control room clean!
==== Report of work (*:responsible person) ====
 * VAC: *Kimura
  * Pump down started ~10am.
Line 61: Line 58:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto
   * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
 * IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
  * Beams from ETMX and ETMY were seen at REFL and showed some interference.
Line 65: Line 61:
 * Green: *Michimura, Yokogawa, Sugimoto
  * Green hits ETMY and IR hits both ends.
  * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
 * DAQ: *Miyakawa
  * k1tw1 started writing minute_raw. All DAQ servers are working stably over the last weekend.
Line 69: Line 64:
 * Tcam:
  * Modifying some mechanical parts at KEK.
==== Work plan (*:responsible person) ====
 * Extended chief meeting at Toyama Univ.
Line 72: Line 67:
 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.
 * VAC: *Kimura
  * Pumping down will start ~10am today.
Line 75: Line 70:
 * PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
Line 77: Line 71:
 * Work plan (*:responsible person)
  * CAL: *Haino
   * To check the safety of laser.
==== Laser hazard ====
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
 * [PM]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 81: Line 79:
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
 * [night]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 85: Line 83:
 * Laser hazard: Upstream SR2-3 line.
Line 87: Line 84:
 * Weekly
  * Week of 2/13
   * Waiting for cooling the mirror.
   * ETMY tuninng.
   * Green setup.
   * 2/16 Preparation for power down.
==== Weekly ====
Line 94: Line 86:
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.
Line 98: Line 91:
  * Week of 2/26
  * Beam alignment to REFL port.
 * week of 4/23
  * Operation
Line 101: Line 94:
  * week of 3/5
   * IYC door will be closed.

  * week of 3/12
   * Vacuum at corner are will be performed in the week.

 * Issues
==== Issues ====
Line 115: Line 101:
==== Weekly meeting ==== === Weekly meeting ===
Line 120: Line 106:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
Line 141: Line 135:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/16(Mon.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • VAC: *Kimura
    • Pump down started ~10am.
  • IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
    • Beams from ETMX and ETMY were seen at REFL and showed some interference.
  • DAQ: *Miyakawa
    • k1tw1 started writing minute_raw. All DAQ servers are working stably over the last weekend.

Work plan (*:responsible person)

  • Extended chief meeting at Toyama Univ.
  • VAC: *Kimura
    • Pumping down will start ~10am today.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)