Line 11: | Line 11: |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 53: | Line 50: |
2017/2/19(Mon.) * Remote participants by eZuce: None * Recovery from the power outage in the morning. * Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned. Glitch is still there but even if measurement with no glitch time has still no coherence. * PR RT models will be modified for Watch dog bug or something. * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs. * Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. * Work plan (*:responsible person) * CAL: *Haino * To check the safety of laser. * ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. * Laser hazard: Upstream SR2-3 line. * Weekly * Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. * Week of 2/26 * Beam alignment to REFL port. * week of 3/5 * IYC door will be closed. * week of 3/12 * Connecting ducts at corner. * Issues |
=== 2018/4/2(Mon.) === * Remote participants by eZuce: Enomoto ==== Report of work (*:responsible person) ==== * ETMX: *Ushiba * Confirmed the returned beam at REFL * Calibration of OpLev is on going (mostly finished) * Start Characterization * ETMY: *Miyamoto * Damping is working well. Less than 2urad RMS. * BS: *Enomoto * Two different problems identified * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero * PCal: Binhua * Aligned the beam within the PCal module * ETMX camera: Yokozawa * Ready but not installed * TMS: no one to report ==== Work plan (*:responsible person) ==== * ETMX: *Ushiba, Miyamoto * Start Characterization * BS: Enomoto * Check the glitches over the weekend * PCal: Binhua * Measure PCal transfer functions * ETMX Camera: Yokozawa * Set up necessary components to take high frame rate pictures ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Work plan (*:responsible person) ==== * ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. * CAL: *Yamamoto * CAL model is tested using iMC. * Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 * Closing EXC ==== Issues ==== * BS: DAC had some glitches but if DAC is off, no glitch was found. |
Line 102: | Line 148: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 107: | Line 153: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || |
|
Line 128: | Line 180: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/2(Mon.)
* Remote participants by eZuce: Enomoto
Report of work (*:responsible person)
* ETMX: *Ushiba
- Confirmed the returned beam at REFL
Calibration of OpLev is on going (mostly finished)
- Start Characterization
* ETMY: *Miyamoto
- Damping is working well. Less than 2urad RMS.
* BS: *Enomoto
- Two different problems identified
Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone
Glitches -> Looks like the same problem as ETMY: DAC output goes to zero
* PCal: Binhua
- Aligned the beam within the PCal module
* ETMX camera: Yokozawa
- Ready but not installed
* TMS: no one to report
Work plan (*:responsible person)
* ETMX: *Ushiba, Miyamoto
- Start Characterization
* BS: Enomoto
- Check the glitches over the weekend
* PCal: Binhua
- Measure PCal transfer functions
* ETMX Camera: Yokozawa
- Set up necessary components to take high frame rate pictures
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Work plan (*:responsible person)
- ETMX: *Ushiba, Takahashi
- Beam will be aligned more precisely with aligned IR.
- CAL: *Yamamoto
- CAL model is tested using iMC.
- Camera: Yokozawa
- EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Closing EXC
Issues
- BS: DAC had some glitches but if DAC is off, no glitch was found.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools