Differences between revisions 302 and 387 (spanning 85 versions)
Revision 302 as of 2018-02-19 09:08:05
Size: 8521
Comment:
Revision 387 as of 2018-04-13 09:17:46
Size: 10895
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 53: Line 50:
=== 2018/4/13(Fri.) ===
Line 54: Line 52:
2017/2/19(Mon.) * Remote participants by eZuce: Miyoki
Line 56: Line 54:
 * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
==== Report of work (*:responsible person) ====
 * IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
  * Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
  * Centering of oplev was done this morning
  * Alignment was tuned IMC from 0.3/1.0->0.7/1.0
  * ETMY damping was improved a bit by Nakano. Now ~3urad.
Line 59: Line 61:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
 * VAC: *Kimura
  * View port for oplev at ETMX was attached yesterday's afternoon.
  * All the preparation was done and the door of EXC was closed.
Line 64: Line 65:
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 67: Line 66:
 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.
==== Work plan (*:responsible person) ====
 * IFO: *Enomoto, Nakano, Nagano
  * Alignment of REFL port aftenoon.
  * Some damping work.
Line 70: Line 71:
 * Work plan (*:responsible person)
  * CAL: *Haino
   * To check the safety of laser.
 * VAC: *Kimura
  * Pumping down will start ~10am today.
Line 74: Line 74:
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
Line 78: Line 75:
 * Laser hazard: Upstream SR2-3 line. ==== Laser hazard ====
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
 * [PM]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 80: Line 83:
 * Weekly
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
 * [night]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 85: Line 87:
  * Week of 2/26
   * Beam alignment to REFL port.
Line 88: Line 88:
  * week of 3/5
   * IYC door will be closed.
==== Weekly ====
Line 91: Line 90:
  * week of 3/12
   * Connecting ducts at corner.
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2.
  * Closing EXC.
  * Some controls for Michelson.
  * 4/13 morning: Pump down starts.
Line 94: Line 96:
 * Issues  * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.
Line 96: Line 101:
 * week of 4/23
  * Operation

==== Issues ====
Line 102: Line 111:
==== Weekly meeting ==== === Weekly meeting ===
Line 107: Line 116:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
Line 128: Line 145:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/13(Fri.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
    • Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
    • Centering of oplev was done this morning
    • Alignment was tuned IMC from 0.3/1.0->0.7/1.0

    • ETMY damping was improved a bit by Nakano. Now ~3urad.
  • VAC: *Kimura
    • View port for oplev at ETMX was attached yesterday's afternoon.
    • All the preparation was done and the door of EXC was closed.

Work plan (*:responsible person)

  • IFO: *Enomoto, Nakano, Nagano
    • Alignment of REFL port aftenoon.
    • Some damping work.
  • VAC: *Kimura
    • Pumping down will start ~10am today.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2.
    • Closing EXC.
    • Some controls for Michelson.
    • 4/13 morning: Pump down starts.
  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)