Differences between revisions 303 and 370 (spanning 67 versions)
Revision 303 as of 2018-02-19 09:16:44
Size: 8398
Comment:
Revision 370 as of 2018-04-05 09:27:32
Size: 10740
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 53: Line 50:
=== 2018/4/5(Thur.) ===
Line 54: Line 52:
2017/2/19(Mon.) * Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Line 56: Line 54:
 * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
==== Report of work (*:responsible person) ====
 * Alignment: Izumi
  * Both light had been confirmed at REFL yesterday morning.
  * IR beam was lost at REFL evening, but green was still seen.
  * Both IR and green were still seen at Y end.
Line 59: Line 60:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
 * ETMX: *Ushiba
  * Circuits and connection are still being checked.
Line 64: Line 63:
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
 * Dolphin: *Yamamoto
  * Connected IMC, IOO and BS.
  * Error indicator is seen on BS.
Line 67: Line 67:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Damping tuning
 * DAQ: *Yamamoto
  * Memory will be increased today. SSD might be tested today at k1tw0.
  * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
  * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
Line 71: Line 72:
 * Laser hazard: Upstream SR2-3 line.  * Vacuum: *Kimura
  * Closing door will be performed in the next week.
Line 73: Line 75:
 * Weekly
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
 * PCal: no one to report
 
 * TMS: no one to report
Line 78: Line 79:
  * Week of 2/26
   * Beam alignment to REFL port.
==== Work plan (*:responsible person) ====
 * Alignment: Izumi
  * IR will be re-aligned this morning. It requires green off evening.
Line 81: Line 83:
  * week of 3/5
   * IYC door will be closed.
 * ETMY: *Miyamoto
  * Cover on Oplev will be set this morning.
Line 84: Line 86:
  * week of 3/12
   * Connecting ducts at corner.
 * DAQ: *Miyakawa
  * Memory will be increased today. SSD might be tested today at k1tw0.
Line 87: Line 89:
 * Issues
  * ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere?

==== Laser hazard ====
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

* [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F


==== Weekly ====

 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.
  * 4/5 12:30 at fan hut: Meeting before pump down 1

 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC

==== Issues ====

Line 95: Line 123:
==== Weekly meeting ==== === Weekly meeting ===
Line 100: Line 128:
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
Line 121: Line 156:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/5(Thur.)

* Remote participants by eZuce: Kimura, Miyoki, Yokozawa

Report of work (*:responsible person)

  • Alignment: Izumi
    • Both light had been confirmed at REFL yesterday morning.
    • IR beam was lost at REFL evening, but green was still seen.
    • Both IR and green were still seen at Y end.
  • ETMX: *Ushiba
    • Circuits and connection are still being checked.
  • Dolphin: *Yamamoto
    • Connected IMC, IOO and BS.
    • Error indicator is seen on BS.
  • DAQ: *Yamamoto
    • Memory will be increased today. SSD might be tested today at k1tw0.
    • Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
    • k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
  • Vacuum: *Kimura
    • Closing door will be performed in the next week.
  • PCal: no one to report
  • TMS: no one to report

Work plan (*:responsible person)

  • Alignment: Izumi
    • IR will be re-aligned this morning. It requires green off evening.
  • ETMY: *Miyamoto
    • Cover on Oplev will be set this morning.
  • DAQ: *Miyakawa
    • Memory will be increased today. SSD might be tested today at k1tw0.

Laser hazard

* [AM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [PM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [night]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

Weekly

  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
    • 4/5 12:30 at fan hut: Meeting before pump down 1
  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)