Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 53: Line 50:
=== 2018/4/12(Thur.) ===
Line 54: Line 52:
2017/2/19(Mon.) * Remote participants by eZuce: None
Line 56: Line 54:
 * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
==== Report of work (*:responsible person) ====
 * IFO: Enomoto, Nagano, Nagano
  * 5 front gate valve opened and beam was verified at the Y end baffle PD.
  * Beam shift was only ~10urad when the gate valve opened.
  * One of the monitor of gate valve did not work.
  * Final check at X end was done.
  * Coil driver for Marionette was changed from low to high.
  * Damping of ETMX will be tested with HPCD.
Line 59: Line 63:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
==== Work plan (*:responsible person) ====
 * IFO: damping work or others.
 * VAC: closing ETMX door.
 * Pumping starts tomorrow morning.
Line 64: Line 68:
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 67: Line 69:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Damping tuning
==== Laser hazard ====
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
 * [PM]
  * IR: PSL, Yend 1F
  * Green: off
Line 71: Line 77:
 * Laser hazard: Upstream SR2-3 line.  * [night]
 * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 73: Line 81:
 * Weekly
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 78: Line 82:
  * Week of 2/26
   * Beam alignment to REFL port.
==== Weekly ====
Line 81: Line 84:
  * week of 3/5
   * IYC door will be closed.
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
  * Some controls for Michelson
  * 4/13 moning Pump down
Line 84: Line 90:
  * week of 3/12
   * Connecting ducts at corner.
 * week of 4/16
  * Michelson control
  * Leak check
Line 87: Line 94:
 * Issues
  * ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere?
 * week of 4/23
  * Operation

==== Issues ====

Line 95: Line 106:
==== Weekly meeting ==== === Weekly meeting ===
Line 100: Line 111:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 122: Line 140:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/12(Thur.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: Enomoto, Nagano, Nagano
    • 5 front gate valve opened and beam was verified at the Y end baffle PD.
    • Beam shift was only ~10urad when the gate valve opened.
    • One of the monitor of gate valve did not work.
    • Final check at X end was done.
    • Coil driver for Marionette was changed from low to high.
    • Damping of ETMX will be tested with HPCD.

Work plan (*:responsible person)

  • IFO: damping work or others.
  • VAC: closing ETMX door.
  • Pumping starts tomorrow morning.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: PSL, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC
    • Some controls for Michelson
    • 4/13 moning Pump down
  • week of 4/16
    • Michelson control
    • Leak check
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings