Line 11: | Line 11: |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 54: | Line 51: |
2017/2/22(Thur.) | 2017/3/29(Thur.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Miyoki | * Remote participants by eZuce: None |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Diagonalizing input matrix. Electronics was something wrong, like oscillation. |
==== Report of work (*:responsible person) ==== |
Line 62: | Line 57: |
* BS: Kozu * Finished measurement the TF of TM and IM coupling. |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Jump of GAS filter was compensated and fixed. * Yaw was roughly aligned by top filter. * First contact was removed. * Top chamber was closed. * Beam reached at the ETMX. * Baffle PD was tested well. |
Line 65: | Line 65: |
* ISS: Koseyama, Sakamoto. * Measuring TF. |
* BS: *Enomoto * We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch. |
Line 68: | Line 68: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
* BRT: Akutsu * Light is collimated well. |
Line 72: | Line 71: |
* Tcam: * Debugging NIKON camera. |
* Camera: Yokozawa * EX camera takes every one hour. * Needs 1 sec picture in the weekend. |
Line 75: | Line 75: |
* IYA monitor: Yokozawa * IYA monitor will start. |
==== Work plan (*:responsible person) ==== |
Line 78: | Line 77: |
* ISS: Koseyama, Kitazawa * Making RT models. |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Mirror will be aligned with beam today. * CAL: *Yamamoto * CAL model is tested using iMC. |
Line 82: | Line 84: |
* Laser hazard: Upstream SR2-3 line. | ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 84: | Line 92: |
* Weekly * Week of 2/19 * ETMY tuninng. |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 88: | Line 96: |
* Week of 2/26 * Beam alignment to REFL port. |
==== Weekly ==== |
Line 91: | Line 98: |
* week of 3/5 * IYC door will be closed. |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
Line 94: | Line 104: |
* week of 3/12 * Exchanging items and cleaning inside the PR2 chamber * Connecting ducts at the corner area. |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
Line 98: | Line 108: |
* week of 3/19 * Vacuum test at at the corner area. |
* week of 4/9 * Closing EXC |
Line 101: | Line 111: |
==== Issues ==== | |
Line 102: | Line 113: |
* Issues * Heat link make some torque. |
* BS: DAC had some glitches with no output (even dac kill and master SW are off). |
Line 110: | Line 121: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 115: | Line 126: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || |
|
Line 137: | Line 153: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/29(Thur.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Jump of GAS filter was compensated and fixed.
- Yaw was roughly aligned by top filter.
- First contact was removed.
- Top chamber was closed.
- Beam reached at the ETMX.
- Baffle PD was tested well.
- BS: *Enomoto
- We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch.
- BRT: Akutsu
- Light is collimated well.
- Camera: Yokozawa
- EX camera takes every one hour.
- Needs 1 sec picture in the weekend.
Work plan (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Mirror will be aligned with beam today.
- CAL: *Yamamoto
- CAL model is tested using iMC.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Closing EXC
Issues
- BS: DAC had some glitches with no output (even dac kill and master SW are off).
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)