Line 11: | Line 11: |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 27: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 53: | Line 39: |
=== 2018/4/28(Sat.) === | |
Line 54: | Line 41: |
2017/2/22(Thur.) | * Remote participants by eZuce: None * 1st day of Phase 1 operation * OLG by |
Line 56: | Line 45: |
* Remote participants by eZuce: Miyoki | ==== Report of work (*:responsible person) ==== |
Line 58: | Line 47: |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Diagonalizing input matrix. Electronics was something wrong, like oscillation. * BS: Kozu * Finished measurement the TF of TM and IM coupling. * ISS: Koseyama, Sakamoto. * Measuring TF. * Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. * Tcam: * Debugging NIKON camera. * IYA monitor: Yokozawa * IYA monitor will start. * ISS: Koseyama, Kitazawa * Making RT models. |
* IFO: *Izumi, Enomoto + many * ETMY damping filter was back to what was best. Fluctuation is ~1urad. * ETMX damping filter changed a bit. Fluctuation is < 1urad. * BS alignment noise was improved around 10-30Hz 8 at most. * Gain bump can be seen around UGF of MICH. * Lock of the last night was ~1hour. Lock was lost because of L to oplev coupling seems to exist. |
Line 82: | Line 55: |
* Laser hazard: Upstream SR2-3 line. | * Camera: Yokozawa, Inoue * IYA camera could not see BS, because some clipping may exist. |
Line 84: | Line 58: |
* Weekly * Week of 2/19 * ETMY tuninng. |
* WAB: Akutsu * Heater off. |
Line 88: | Line 61: |
* Week of 2/26 * Beam alignment to REFL port. |
* IYC: Tomaru * Cooler off. |
Line 91: | Line 64: |
* week of 3/5 * IYC door will be closed. |
* Operaton: * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened. |
Line 94: | Line 67: |
* week of 3/12 * Exchanging items and cleaning inside the PR2 chamber * Connecting ducts at the corner area. |
==== Work plan (*:responsible person) ==== |
Line 98: | Line 69: |
* week of 3/19 * Vacuum test at at the corner area. |
* CAL: Yamamoto * Optical gain measurement * Open loot TF. * Amplitude tuning for injection. * Sensitivity. * BS to MICH TF, if can. * IFO: *Izumi, Enomoto + many * Higher BS oplev gain will be tried today by the gain switch on opec board or the gain setting on whitening board. |
Line 102: | Line 80: |
* Issues * Heat link make some torque. |
==== Laser hazard ==== * [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== * week of 4/23 * Michelson control. * 4/28 Operation start * week of 4/30 * Operation continues. ==== Issues ==== |
Line 110: | Line 111: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 115: | Line 116: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || |
|
Line 137: | Line 146: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/28(Sat.)
* Remote participants by eZuce: None * 1st day of Phase 1 operation
- OLG by
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- ETMY damping filter was back to what was best. Fluctuation is ~1urad.
ETMX damping filter changed a bit. Fluctuation is < 1urad.
- BS alignment noise was improved around 10-30Hz 8 at most.
- Gain bump can be seen around UGF of MICH.
- Lock of the last night was ~1hour. Lock was lost because of L to oplev coupling seems to exist.
- Camera: Yokozawa, Inoue
- IYA camera could not see BS, because some clipping may exist.
- WAB: Akutsu
- Heater off.
- IYC: Tomaru
- Cooler off.
- Operaton:
Operation wiki page is opened.
Work plan (*:responsible person)
- CAL: Yamamoto
- Optical gain measurement
- Open loot TF.
- Amplitude tuning for injection.
- Sensitivity.
- BS to MICH TF, if can.
- IFO: *Izumi, Enomoto + many
- Higher BS oplev gain will be tried today by the gain switch on opec board or the gain setting on whitening board.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)