Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 54: Line 51:
2017/2/22(Thur.) 2017/3/23(Fri.)
Line 56: Line 53:
 * Remote participants by eZuce: Miyoki  * Remote participants by eZuce: Izumi, Miyoki
Line 58: Line 55:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Diagonalizing input matrix. Electronics was something wrong, like oscillation.
==== Report of work (*:responsible person) ====
Line 62: Line 57:
  * BS: Kozu
   * Finished measurement the TF of TM and IM coupling.
 * IFO: *Izumi, Miyamoto, Eleonora
  * BS had some difficulty to close control loop of Y of oplev.
  * T of ETMY control loop was closed.
  * Circuits of baffle PD are being prepared.
Line 65: Line 62:
  * ISS: Koseyama, Sakamoto.
   * Measuring TF.
 * AOS: *Akutsu, Yokogawa
  * Green team succeeded to reach green and IR to ETMY.
  * BRT alignment is going on yesterday and today.
  * Oplev is being prepared at EXC.
Line 68: Line 67:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.

  * ISS: Koseyama, Kitazawa
   * Making RT models.
 * Camera: Yokozawa, Yamamoto, Miyamoto
  * X end camera will be recovered.
  * IYC cooling started.
Line 76: Line 72:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line. ==== Work plan (*:responsible person) ====
Line 78: Line 74:
 * Weekly
  * Week of 2/19
   * ETMY tuninng.
 * Alignment: *Eleonora, Miyamoto
  * BS diagonalization
  * ETMY damping
Line 82: Line 78:
  * Week of 2/26
   * Beam alignment to REFL port.
   * Height change for PRs

  * week of 3/5
   * IYC door will be closed.

  * week of 3/12
   * Exchanging items and cleaning inside the PR2 chamber
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
 * AOS: *Akutsu, Yokogawa
  * BRT alignment is going on yesterday and today.
  * Oplev work at EXC.
Line 97: Line 83:
==== Laser hazard ====
 * [AM]
  * IR: PSL
  * Green: around PR2
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
  * Green: Xend 1F.

 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
  * Green: Xend 1F.

==== Weekly ====

 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21~: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa

 * week of 3/26
  * Rough alignment of ETMX is planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
Line 98: Line 108:
Line 104: Line 115:
==== Weekly meeting ==== === Weekly meeting ===
Line 109: Line 120:
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 131: Line 146:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/23(Fri.)

  • Remote participants by eZuce: Izumi, Miyoki

Report of work (*:responsible person)

  • IFO: *Izumi, Miyamoto, Eleonora
    • BS had some difficulty to close control loop of Y of oplev.
    • T of ETMY control loop was closed.
    • Circuits of baffle PD are being prepared.
  • AOS: *Akutsu, Yokogawa
    • Green team succeeded to reach green and IR to ETMY.
    • BRT alignment is going on yesterday and today.
    • Oplev is being prepared at EXC.
  • Camera: Yokozawa, Yamamoto, Miyamoto
    • X end camera will be recovered.
    • IYC cooling started.

Work plan (*:responsible person)

  • Alignment: *Eleonora, Miyamoto
    • BS diagonalization
    • ETMY damping
  • AOS: *Akutsu, Yokogawa
    • BRT alignment is going on yesterday and today.
    • Oplev work at EXC.

Laser hazard

  • [AM]
    • IR: PSL
    • Green: around PR2
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
    • Green: Xend 1F.
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
    • Green: Xend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21~: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX is planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)