Line 11: | Line 11: |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 54: | Line 51: |
2017/2/22(Thur.) | 2017/3/27(Tue.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Miyoki | * Remote participants by eZuce: Yokozawa |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Diagonalizing input matrix. Electronics was something wrong, like oscillation. |
==== Report of work (*:responsible person) ==== |
Line 62: | Line 57: |
* BS: Kozu * Finished measurement the TF of TM and IM coupling. |
* Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY * All are free except for Pre-isolator. * Cable connections seemed to be fine. * First contact will be removed. |
Line 65: | Line 62: |
* ISS: Koseyama, Sakamoto. * Measuring TF. |
* Oplev at ETMX: Akutsu * Preparation is almost done. |
Line 68: | Line 65: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. * ISS: Koseyama, Kitazawa * Making RT models. |
* BS: *Enomoto * Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model. |
Line 76: | Line 69: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line. | ==== Work plan (*:responsible person) ==== |
Line 78: | Line 71: |
* Weekly * Week of 2/19 * ETMY tuninng. |
* Camera: *Inoue, Yokozawa * ETMX PD will be removed. * GigE camera will be removed today and placed next week. |
Line 82: | Line 75: |
* Week of 2/26 * Beam alignment to REFL port. * Height change for PRs |
* Oplev at ETMX: *Akutsu, Simon * Once first contact is removed, opelev will be aligned. |
Line 86: | Line 78: |
* week of 3/5 * IYC door will be closed. |
* BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto * Alignment |
Line 89: | Line 81: |
* week of 3/12 * Exchanging items and cleaning inside the PR2 chamber * Connecting ducts at the corner area. |
==== Laser hazard ==== * [AM] * IR: PSL * Green: PR2 * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 93: | Line 89: |
* week of 3/19 * Vacuum test at at the corner area. |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== * week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 |
Line 98: | Line 110: |
Line 104: | Line 117: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 109: | Line 122: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || |
|
Line 131: | Line 149: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/27(Tue.)
- Remote participants by eZuce: Yokozawa
Report of work (*:responsible person)
- Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY
- All are free except for Pre-isolator.
- Cable connections seemed to be fine.
- First contact will be removed.
- Oplev at ETMX: Akutsu
- Preparation is almost done.
- BS: *Enomoto
- Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model.
Work plan (*:responsible person)
- Camera: *Inoue, Yokozawa
- ETMX PD will be removed.
- GigE camera will be removed today and placed next week.
- Oplev at ETMX: *Akutsu, Simon
- Once first contact is removed, opelev will be aligned.
- BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto
- Alignment
Laser hazard
- [AM]
- IR: PSL
- Green: PR2
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)