9143
Comment:
|
9826
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 54: | Line 51: |
2017/2/23(Fri.) | 2017/3/20(Tue.) |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified. * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
==== Report of work (*:responsible person) ==== |
Line 63: | Line 57: |
* ETMY Camera is still under debugging. Camera seems to be broken. * ITMY camera was aligned, and needs focus next. * IOO: Kitazawa * working for guardian. |
* VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. * Alignment: *Izumi * All alignment to REFL after pump down was verified. * Only ETMY was off position by ~100urad. * ETMY: *Miyamoto * Diagonal of sensors. Still going on. * BS: Eleonora, Izumi * Coil balance is going on. * IMC: * "sleep" commands were removed from Guardian. * Cal: Yokozawa * We checked all the IMC TFs. |
Line 69: | Line 77: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
|
Line 73: | Line 78: |
* ISS: Koseyama, Kitazawa * Making RT models. |
==== Work plan (*:responsible person) ==== * Alignment, ETMY: *Izumi * Cal: Yokozawa * Injection will be tested soon. |
Line 77: | Line 86: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | ==== Laser hazard ==== * [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
Line 79: | Line 91: |
* Weekly * Week of 2/19 * ETMY tuninng. |
==== Weekly ==== |
Line 83: | Line 93: |
* Week of 2/26 * Beam alignment to REFL port. * 2/28: Height change for PRs |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
Line 87: | Line 99: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
Line 101: | Line 104: |
* The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified. * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
|
Line 109: | Line 111: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 114: | Line 116: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || |
|
Line 136: | Line 142: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/20(Tue.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- PR2 assembly frames will be removed soon.
- Alignment: *Izumi
- All alignment to REFL after pump down was verified.
- Only ETMY was off position by ~100urad.
- All alignment to REFL after pump down was verified.
- ETMY: *Miyamoto
- Diagonal of sensors. Still going on.
- BS: Eleonora, Izumi
- Coil balance is going on.
- IMC:
- "sleep" commands were removed from Guardian.
- Cal: Yokozawa
- We checked all the IMC TFs.
Work plan (*:responsible person)
- Alignment, ETMY: *Izumi
- Cal: Yokozawa
- Injection will be tested soon.
Laser hazard
- [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX will be planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools