Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 54: Line 51:
2017/2/23(Fri.) 2017/3/23(Fri.)
Line 56: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Izumi, Miyoki
Line 58: Line 55:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
==== Report of work (*:responsible person) ====
Line 63: Line 57:
  * ETMY Camera is still under debugging. Camera seems to be broken.
  * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa
   * working for guardian.
 * IFO: *Izumi, Miyamoto, Eleonora
  * BS had some difficulty to close control loop of Y of oplev.
  * T of ETMY control loop was closed.
  * Circuits of baffle PD are being prepared.

 * AOS: *Akutsu, Yokogawa
  * Green team succeeded to reach green and IR to ETMY.
  * BRT alignment is going on yesterday and today.
  * Oplev is being prepared at EXC.

 * Camera: Yokozawa, Yamamoto, Miyamoto
  * X end camera will be recovered.
  * IYC cooling started.
Line 69: Line 72:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
==== Work plan (*:responsible person) ====
Line 73: Line 74:
  * ISS: Koseyama, Kitazawa
   * Making RT models.
 * Alignment: *Eleonora, Miyamoto
  * BS diagonalization
  * ETMY damping

 * AOS: *Akutsu, Yokogawa
  * BRT alignment is going on yesterday and today.
  * Oplev work at EXC.
Line 77: Line 83:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. ==== Laser hazard ====
 * [
AM]
  * IR
: PSL
  * Green: around
PR2
 * [P
M]
  * IR
: Upstream SR2-3 line, Xend 1F, Yend 1F.
  * Green: Xend 1F.
Line 79: Line 91:
 * Weekly
  * Week of 2/19
   * ETMY tuninng.
 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
  * Green: Xend 1F.
Line 83: Line 95:
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
==== Weekly ====
Line 87: Line 97:
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21~: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa
Line 91: Line 103:
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
 * week of 3/26
  * Rough alignment of ETMX is planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
Line 101: Line 108:
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 109: Line 115:
==== Weekly meeting ==== === Weekly meeting ===
Line 114: Line 120:
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 136: Line 146:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/23(Fri.)

  • Remote participants by eZuce: Izumi, Miyoki

Report of work (*:responsible person)

  • IFO: *Izumi, Miyamoto, Eleonora
    • BS had some difficulty to close control loop of Y of oplev.
    • T of ETMY control loop was closed.
    • Circuits of baffle PD are being prepared.
  • AOS: *Akutsu, Yokogawa
    • Green team succeeded to reach green and IR to ETMY.
    • BRT alignment is going on yesterday and today.
    • Oplev is being prepared at EXC.
  • Camera: Yokozawa, Yamamoto, Miyamoto
    • X end camera will be recovered.
    • IYC cooling started.

Work plan (*:responsible person)

  • Alignment: *Eleonora, Miyamoto
    • BS diagonalization
    • ETMY damping
  • AOS: *Akutsu, Yokogawa
    • BRT alignment is going on yesterday and today.
    • Oplev work at EXC.

Laser hazard

  • [AM]
    • IR: PSL
    • Green: around PR2
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
    • Green: Xend 1F.
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F.
    • Green: Xend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21~: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX is planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1