Differences between revisions 312 and 363 (spanning 51 versions)
Revision 312 as of 2018-02-23 09:13:00
Size: 9143
Comment:
Revision 363 as of 2018-03-29 09:18:48
Size: 10477
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 54: Line 51:
2017/2/23(Fri.) 2017/3/29(Thur.)
Line 58: Line 55:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
==== Report of work (*:responsible person) ====
Line 63: Line 57:
  * ETMY Camera is still under debugging. Camera seems to be broken.
  * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa
   * working for guardian.
 * ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
  * Jump of GAS filter was compensated and fixed.
  * Yaw was roughly aligned by top filter.
  * First contact was removed.
  * Top chamber was closed.
  * Beam reached at the ETMX.
  * Baffle PD was tested well.

 * BS: *Enomoto
  * We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch.

 * BRT: Akutsu
  * Light is collimated well.

 * Camera: Yokozawa
  * EX camera takes every one hour.
  * Needs 1 sec picture in the weekend.

==== Work plan (*:responsible person) ====

 * ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
  * Mirror will be aligned with beam today.

 * CAL: *Yamamoto
  * CAL model is tested using iMC.
Line 69: Line 84:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
==== Laser hazard ====
 * [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 73: Line 92:
  * ISS: Koseyama, Kitazawa
   * Making RT models.
 * [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 76: Line 96:
==== Weekly ====
Line 77: Line 98:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.  * week of 3/26
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * 3/27 EX PD will be removed.: *Yokozawa
Line 79: Line 104:
 * Weekly
  * Week of 2/19
   * ETMY tuninng.
 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.
Line 83: Line 108:
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
 * week of 4/9
  * Closing EXC
Line 87: Line 111:
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
==== Issues ====
Line 91: Line 113:
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.
 * BS: DAC had some glitches with no output (even dac kill and master SW are off).
Line 95: Line 115:
  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.


 * Issues
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 109: Line 121:
==== Weekly meeting ==== === Weekly meeting ===
Line 114: Line 126:
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 136: Line 153:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/29(Thur.)

  • Remote participants by eZuce: None

Report of work (*:responsible person)

  • ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
    • Jump of GAS filter was compensated and fixed.
    • Yaw was roughly aligned by top filter.
    • First contact was removed.
    • Top chamber was closed.
    • Beam reached at the ETMX.
    • Baffle PD was tested well.
  • BS: *Enomoto
    • We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch.
  • BRT: Akutsu
    • Light is collimated well.
  • Camera: Yokozawa
    • EX camera takes every one hour.
    • Needs 1 sec picture in the weekend.

Work plan (*:responsible person)

  • ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
    • Mirror will be aligned with beam today.
  • CAL: *Yamamoto
    • CAL model is tested using iMC.

Laser hazard

  • [AM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 3/26
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
    • Connection of cable at ETMX and starting control.
    • Rough alignment of ETMX using IR.
      • 3/27 EX PD will be removed.: *Yokozawa
  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
  • week of 4/9
    • Closing EXC

Issues

  • BS: DAC had some glitches with no output (even dac kill and master SW are off).

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)