Line 11: | Line 11: |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 53: | Line 50: |
=== 2018/4/5(Thur.) === | |
Line 54: | Line 52: |
2017/2/23(Fri.) | * Remote participants by eZuce: Kimura, Miyoki, Yokozawa |
Line 56: | Line 54: |
* Remote participants by eZuce: None | ==== Report of work (*:responsible person) ==== * Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. |
Line 58: | Line 60: |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified. * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
* ETMX: *Ushiba * Circuits and connection are still being checked. |
Line 63: | Line 63: |
* ETMY Camera is still under debugging. Camera seems to be broken. * ITMY camera was aligned, and needs focus next. * IOO: Kitazawa * working for guardian. |
* Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. * DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. * Vacuum: *Kimura * Closing door will be performed in the next week. * PCal: no one to report * TMS: no one to report ==== Work plan (*:responsible person) ==== * Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. * ETMY: *Miyamoto * Cover on Oplev will be set this morning. * DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
Line 69: | Line 90: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 73: | Line 98: |
* ISS: Koseyama, Kitazawa * Making RT models. |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 77: | Line 103: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | ==== Weekly ==== |
Line 79: | Line 105: |
* Weekly * Week of 2/19 * ETMY tuninng. |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
Line 83: | Line 110: |
* Week of 2/26 * Beam alignment to REFL port. * 2/28: Height change for PRs |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
Line 87: | Line 114: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
==== Issues ==== |
Line 100: | Line 117: |
* Issues * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified. * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
|
Line 109: | Line 123: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 114: | Line 128: |
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || |
|
Line 136: | Line 156: |
* Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/5(Thur.)
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Report of work (*:responsible person)
- Alignment: Izumi
- Both light had been confirmed at REFL yesterday morning.
- IR beam was lost at REFL evening, but green was still seen.
- Both IR and green were still seen at Y end.
- ETMX: *Ushiba
- Circuits and connection are still being checked.
- Dolphin: *Yamamoto
- Connected IMC, IOO and BS.
- Error indicator is seen on BS.
- DAQ: *Yamamoto
- Memory will be increased today. SSD might be tested today at k1tw0.
- Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
- k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
- Vacuum: *Kimura
- Closing door will be performed in the next week.
- PCal: no one to report
- TMS: no one to report
Work plan (*:responsible person)
- Alignment: Izumi
- IR will be re-aligned this morning. It requires green off evening.
- ETMY: *Miyamoto
- Cover on Oplev will be set this morning.
- DAQ: *Miyakawa
- Memory will be increased today. SSD might be tested today at k1tw0.
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools