Differences between revisions 312 and 377 (spanning 65 versions)
Revision 312 as of 2018-02-23 09:13:00
Size: 9143
Comment:
Revision 377 as of 2018-04-10 09:15:01
Size: 10272
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 53: Line 50:
=== 2018/4/11(Tue.) ===
Line 54: Line 52:
2017/2/23(Fri.) * Remote participants by eZuce: None
Line 56: Line 54:
 * Remote participants by eZuce: None ==== Report of work (*:responsible person) ====
 * IFO: Enomoto, Nagano, Machimura, Takano
  * Michelson fringe was seen at the REFL port.
  * ETMY is still moving a lot.
  * IMC was aligned again. PLS is going lower. Then PR3 was aligned.
  * Oplev of EMX was a good reference to align to REFL.
  * REFL port has been aligned roughly.
Line 58: Line 62:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.

  * ETMY Camera is still under debugging. Camera seems to be broken.
  * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa
   * working for guardian.
 * DGS: Yamamoto
  * We have found how to stop/start Dolphin without stopping RT models connected to Dolphin.
Line 69: Line 66:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
==== Work plan (*:responsible person) ====
 * Camera: Inoue, Yokozawa
  * Illuminator will be installed.
  * We check that nothing blocks the beam between IXA and IXC.
Line 73: Line 71:
  * ISS: Koseyama, Kitazawa
   * Making RT models.
 * DAQ: *Miyakawa
  * Recording minute raw date will start again at k1tw0 this morning.
Line 77: Line 75:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. ==== Laser hazard ====
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
 * [PM]
  * IR: PSL, Yend 1F
  * Green: off
Line 79: Line 83:
 * Weekly
  * Week of 2/19
   * ETMY tuninng.

  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
 * [night]
  * IR: PSL, Yend 1F
  * Green: off
Line 100: Line 88:
 * Issues
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
==== Weekly ====

 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
  * Some controls for Michelson

==== Issues ====

Line 109: Line 104:
==== Weekly meeting ==== === Weekly meeting ===
Line 114: Line 109:
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 136: Line 137:
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/11(Tue.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: Enomoto, Nagano, Machimura, Takano
    • Michelson fringe was seen at the REFL port.
    • ETMY is still moving a lot.
    • IMC was aligned again. PLS is going lower. Then PR3 was aligned.
    • Oplev of EMX was a good reference to align to REFL.
    • REFL port has been aligned roughly.
  • DGS: Yamamoto
    • We have found how to stop/start Dolphin without stopping RT models connected to Dolphin.

Work plan (*:responsible person)

  • Camera: Inoue, Yokozawa
    • Illuminator will be installed.
    • We check that nothing blocks the beam between IXA and IXC.
  • DAQ: *Miyakawa
    • Recording minute raw date will start again at k1tw0 this morning.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: PSL, Yend 1F
    • Green: off
  • [night]
    • IR: PSL, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC
    • Some controls for Michelson

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)