Differences between revisions 312 and 394 (spanning 82 versions)
Revision 312 as of 2018-02-23 09:13:00
Size: 9143
Comment:
Revision 394 as of 2018-04-19 09:14:55
Size: 11255
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 53: Line 50:
=== 2018/4/19(Thur.) ===
Line 54: Line 52:
2017/2/23(Fri.) * Remote participants by eZuce: Miyoki
Line 56: Line 54:
 * Remote participants by eZuce: None ==== Report of work (*:responsible person) ====
 * Phase 1 operation was postponed to 4/28 start.
Line 58: Line 57:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
 * VAC: *Kimura
  * Large leak was found at the door on the cross tube, and started venting ~15:00. It takes almost one day to start fix the door, will be afternoon today. Pump down will start tomorrow morning.
  * Leak test will be performed on Sunday morning.
Line 63: Line 61:
  * ETMY Camera is still under debugging. Camera seems to be broken.
  * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa
   * working for guardian.
 * ETMX: *Hasegawa
  * Transfer function of TM to BF is being investigated.

 * ETMY: *Nakano, Shishido
  * One of the 1.64 and 1.66 Hz peak was suppressed but other one was not. 1-2urad in yaw, 10urad in pitch.
  * RMS motion at REFL port is still dominated by ETMY.

 * BS: *Eleonora, Izumi
  * We are optimizing diagonalization of L2P filter. Needs more time. RMS ~urad
Line 69: Line 72:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
==== Work plan (*:responsible person) ====
Line 73: Line 74:
  * ISS: Koseyama, Kitazawa
   * Making RT models.
 * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
  * Damping, BS L2P, restoring alignment.

 * VAC: *Kimura
  * To fix large and small leaks.
Line 77: Line 81:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. ==== Laser hazard ====
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 79: Line 89:
 * Weekly
  * Week of 2/19
   * ETMY tuninng.

  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 100: Line 94:
 * Issues
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
==== Weekly ====

 * week of 4/16
  * Michelson control.
  * Leak check, and fix leaks.

 * week of 4/23
  * Opening the last gate valve.
  * 4/28 Operation start

==== Issues ====
Line 109: Line 112:
==== Weekly meeting ==== === Weekly meeting ===
Line 114: Line 117:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 136: Line 147:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/19(Thur.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • Phase 1 operation was postponed to 4/28 start.
  • VAC: *Kimura
    • Large leak was found at the door on the cross tube, and started venting ~15:00. It takes almost one day to start fix the door, will be afternoon today. Pump down will start tomorrow morning.
    • Leak test will be performed on Sunday morning.
  • ETMX: *Hasegawa
    • Transfer function of TM to BF is being investigated.
  • ETMY: *Nakano, Shishido
    • One of the 1.64 and 1.66 Hz peak was suppressed but other one was not. 1-2urad in yaw, 10urad in pitch.
    • RMS motion at REFL port is still dominated by ETMY.
  • BS: *Eleonora, Izumi
    • We are optimizing diagonalization of L2P filter. Needs more time. RMS ~urad

Work plan (*:responsible person)

  • IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • To fix large and small leaks.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check, and fix leaks.
  • week of 4/23
    • Opening the last gate valve.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)