Differences between revisions 313 and 354 (spanning 41 versions)
Revision 313 as of 2018-02-23 09:16:23
Size: 9215
Comment:
Revision 354 as of 2018-03-22 11:06:17
Size: 10282
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 54: Line 51:
2017/2/23(Fri.) 2017/3/21(Thur.)
Line 56: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Kimura, Miyoki
Line 58: Line 55:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
==== Report of work (*:responsible person) ====
Line 63: Line 57:
  * Camera: Inoue, Haino, Yokozawa, Cory, Binhua
   * ETMY Camera is still under debugging. Camera seems to be broken.
   * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa, kokeyama
   * Making guardian script for ISS.
 * IFO: *Izumi, Miyamoto, Eleonora
  * Daily Beam check was confirmed at the REFL port yesterday evening.
  * Measurement of BS sensing and driving matrix and diagonalizarion of them.
   * This method should be automatically performed, but still we needs some work to be done.
  * T of ETMY was checked and improved. We need the same work for L.
  * LSC screen has been updated.

  * AOS: *Akutsu, Yokogawa
   * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
Line 70: Line 68:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.

  * ISS: Koseyama, Kitazawa
   * Making RT models.
 * IMC, CAL: Yokozawa, Yamamoto, Miyamoto
  * IMC Transmitted light is too low. Alignment should be checked.
  * Injection to MCE for calibration was tested.
  
 * VAC: Uchiyama
  * Vacuum level of X arm is degraded.
Line 78: Line 76:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. ==== Work plan (*:responsible person) ====
Line 80: Line 78:
 * Weekly
  * Week of 2/19
   * ETMY tuninng.
 * Alignment: *Izumi
  * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
   * Needs power supply for QPD.
Line 84: Line 82:
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
 * AOS: *Akutsu, Yokogawa
  * TMS alignment at ETMY.
  * Cooling will start at 10AM.
Line 101: Line 87:
==== Laser hazard ====
 * [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.

==== Weekly ====

 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21~: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa

 * week of 3/26
  * Rough alignment of ETMX will be planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
Line 102: Line 105:
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 110: Line 112:
==== Weekly meeting ==== === Weekly meeting ===
Line 115: Line 117:
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 137: Line 143:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/21(Thur.)

  • Remote participants by eZuce: Kimura, Miyoki

Report of work (*:responsible person)

  • IFO: *Izumi, Miyamoto, Eleonora
    • Daily Beam check was confirmed at the REFL port yesterday evening.
    • Measurement of BS sensing and driving matrix and diagonalizarion of them.
      • This method should be automatically performed, but still we needs some work to be done.
    • T of ETMY was checked and improved. We need the same work for L.
    • LSC screen has been updated.
    • AOS: *Akutsu, Yokogawa
      • Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
  • IMC, CAL: Yokozawa, Yamamoto, Miyamoto
    • IMC Transmitted light is too low. Alignment should be checked.
    • Injection to MCE for calibration was tested.
  • VAC: Uchiyama
    • Vacuum level of X arm is degraded.

Work plan (*:responsible person)

  • Alignment: *Izumi
    • ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
      • Needs power supply for QPD.
  • AOS: *Akutsu, Yokogawa
    • TMS alignment at ETMY.
    • Cooling will start at 10AM.

Laser hazard

  • [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21~: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX will be planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)