9215
Comment:
|
10496
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Izumi |
|
Line 54: | Line 51: |
2017/2/23(Fri.) | 2017/3/30(Fri.) |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified. * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
==== Report of work (*:responsible person) ==== |
Line 63: | Line 57: |
* Camera: Inoue, Haino, Yokozawa, Cory, Binhua * ETMY Camera is still under debugging. Camera seems to be broken. * ITMY camera was aligned, and needs focus next. * IOO: Kitazawa, kokeyama * Making guardian script for ISS. |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano * Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well. * Oplev is placed but not calibrated. * LVDT of BF seems to be something wrong. It could be satellite box. * BS: *Enomoto, Enzo * Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains. * Hyper threading should be off. * BRT: Nagano * TMS was seen and aligned to QPD. |
Line 70: | Line 70: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
* |
Line 74: | Line 72: |
* ISS: Koseyama, Kitazawa * Making RT models. |
==== Work plan (*:responsible person) ==== * ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. * CAL: *Yamamoto * CAL model is tested using iMC. * Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. |
Line 78: | Line 84: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 80: | Line 92: |
* Weekly * Week of 2/19 * ETMY tuninng. |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 84: | Line 96: |
* Week of 2/26 * Beam alignment to REFL port. * 2/28: Height change for PRs |
==== Weekly ==== |
Line 88: | Line 98: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
Line 92: | Line 104: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
Line 96: | Line 108: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* week of 4/9 * Closing EXC |
Line 100: | Line 111: |
==== Issues ==== | |
Line 101: | Line 113: |
* Issues * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified. * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
* BS: DAC had some glitches but if DAC is off, no glitch was found. |
Line 110: | Line 121: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 115: | Line 126: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || |
|
Line 137: | Line 153: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/30(Fri.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano
- Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well.
- Oplev is placed but not calibrated.
- LVDT of BF seems to be something wrong. It could be satellite box.
- BS: *Enomoto, Enzo
- Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains.
- Hyper threading should be off.
- BRT: Nagano
- TMS was seen and aligned to QPD.
Work plan (*:responsible person)
- ETMX: *Ushiba, Takahashi
- Beam will be aligned more precisely with aligned IR.
- CAL: *Yamamoto
- CAL model is tested using iMC.
- Camera: Yokozawa
- EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Closing EXC
Issues
- BS: DAC had some glitches but if DAC is off, no glitch was found.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools