Differences between revisions 313 and 403 (spanning 90 versions)
Revision 313 as of 2018-02-23 09:16:23
Size: 9215
Comment:
Revision 403 as of 2018-04-27 09:31:05
Size: 11289
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Izumi
Line 27: Line 24:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
Line 53: Line 39:
=== 2018/4/27(Fri.) ===
Line 54: Line 41:
2017/2/23(Fri.) * Remote participants by eZuce: None
Line 56: Line 43:
 * Remote participants by eZuce: None ==== Report of work (*:responsible person) ====
Line 58: Line 45:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
 * IFO: *Izumi, Enomoto + many
  * Michelson lock lasted longer than 2 and half hours!
  * Alignment control from IFO to ETMX was implemented by dithering ETMX.
  * RT models for PR2 and PR3 were down sampled from 16kHz to 2kHz. (Ushiba)
  * PR3 alignment was implemented by baffle signal.
  * ETMX damping might be a cause of lock lost.
  * ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
  * BS oplev is fed back to not only TM but also IM. (Arai)
Line 63: Line 54:
  * Camera: Inoue, Haino, Yokozawa, Cory, Binhua
   * ETMY Camera is still under debugging. Camera seems to be broken.
   * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa, kokeyama
   * Making guardian script for ISS.
 * WAB: *Akutsu
  * Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
  * Equilibrium temperature was 21K.
  * Damping became to strong in low temperature.

 * SR: *Mark, Enzo, Tanioka, Kozu
  * Wire of RM was broken on SR3 during tightening clamp. There was no damage.

 * CAL: *Yamamoto
  * Line injection is being tested.
  * UGF serve will not be implemented, so change of optical gain is compensated in off line.

 * Operaton:
  * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened.
  * Operation schedule and emergency contact list is put on the white board in the control room.

==== Work plan (*:responsible person) ====

 * IFO: *Izumi, Enomoto, Nakano + many
  * Measurement without locking morning, measurement with locking in the afternoon.
Line 70: Line 76:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
==== Laser hazard ====
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 74: Line 84:
  * ISS: Koseyama, Kitazawa
   * Making RT models.
 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 78: Line 89:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. ==== Weekly ====
Line 80: Line 91:
 * Weekly
  * Week of 2/19
   * ETMY tuninng.
 * week of 4/23
  * Michelson control.
  * 4/28 Operation start
Line 84: Line 95:
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
==== Issues ====
Line 101: Line 98:
 * Issues
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 110: Line 104:
==== Weekly meeting ==== === Weekly meeting ===
Line 115: Line 109:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
Line 137: Line 139:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/27(Fri.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto + many
    • Michelson lock lasted longer than 2 and half hours!
    • Alignment control from IFO to ETMX was implemented by dithering ETMX.
    • RT models for PR2 and PR3 were down sampled from 16kHz to 2kHz. (Ushiba)
    • PR3 alignment was implemented by baffle signal.
    • ETMX damping might be a cause of lock lost.
    • ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
    • BS oplev is fed back to not only TM but also IM. (Arai)
  • WAB: *Akutsu
    • Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
    • Equilibrium temperature was 21K.
    • Damping became to strong in low temperature.
  • SR: *Mark, Enzo, Tanioka, Kozu
    • Wire of RM was broken on SR3 during tightening clamp. There was no damage.
  • CAL: *Yamamoto
    • Line injection is being tested.
    • UGF serve will not be implemented, so change of optical gain is compensated in off line.
  • Operaton:
    • Operation wiki page is opened.

    • Operation schedule and emergency contact list is put on the white board in the control room.

Work plan (*:responsible person)

  • IFO: *Izumi, Enomoto, Nakano + many
    • Measurement without locking morning, measurement with locking in the afternoon.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)