Line 11: | Line 11: |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/2/26(Mon.) | 2017/3/26(Mon.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Miyoki | * Remote participants by eZuce: Shoda |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Enomoto * Photo sensor noise was improved on Thursday and checked on Friday. We confirmed the noise becomes better. * Sampling model of RT model was changed from 16kHz to 2kHz to reduce 10min period glitch. |
==== Report of work (*:responsible person) ==== |
Line 63: | Line 57: |
* Camera: Inoue, Haino, Yokozawa, Cory, Binhua * ETMY Camera was broken by taking too many photos. Camera will be replaced. * ITMY camera is being set to look at BS. * BS PD will be replaced by Yokozawa. |
* ETMY: *Miyamoto * Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close! |
Line 68: | Line 60: |
* IOO: Kitazawa, kokeyama * IO chassis will be replaced and being prepared. |
* BS: *Eleonora, Yamamoto * DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently. |
Line 71: | Line 63: |
* CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
* Camera: *Inoue * X end camera was recovered, needs PC tuning. * Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
Line 75: | Line 71: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
==== Work plan (*:responsible person) ==== |
Line 80: | Line 73: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | * BS: *Enomonot * Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week. |
Line 82: | Line 76: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
* AOS: *Akutsu, Yokogawa * BRT alignment is still going on. * Oplev work at EXC. It will be available early this week. |
Line 88: | Line 80: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
|
Line 92: | Line 81: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
==== Laser hazard ==== * [AM] * IR: PSL * Green: none * [PM] * IR: PSL * Green: none |
Line 96: | Line 89: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* [night] * IR: PSL * Green: none ==== Weekly ==== * week of 3/26 * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * EX PD will be removed.: *Yokozawa * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 |
Line 102: | Line 110: |
* DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. | |
Line 109: | Line 117: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 114: | Line 122: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || |
|
Line 136: | Line 148: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/20 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/26(Mon.)
- Remote participants by eZuce: Shoda
Report of work (*:responsible person)
- ETMY: *Miyamoto
- Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close!
- BS: *Eleonora, Yamamoto
- DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently.
- Camera: *Inoue
- X end camera was recovered, needs PC tuning.
- Camera: Yokozawa, Yamamoto, Miyamoto
- X end camera will be recovered.
- IYC cooling started.
Work plan (*:responsible person)
- BS: *Enomonot
- Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week.
- AOS: *Akutsu, Yokogawa
- BRT alignment is still going on.
- Oplev work at EXC. It will be available early this week.
Laser hazard
- [AM]
- IR: PSL
- Green: none
- [PM]
- IR: PSL
- Green: none
- [night]
- IR: PSL
- Green: none
Weekly
- week of 3/26
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- EX PD will be removed.: *Yokozawa
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)