Differences between revisions 315 and 390 (spanning 75 versions)
Revision 315 as of 2018-02-26 14:26:42
Size: 9402
Comment:
Revision 390 as of 2018-04-17 09:17:36
Size: 11281
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 53: Line 50:
=== 2018/4/17(Tue.) ===
Line 54: Line 52:
2017/2/26(Mon.) * Remote participants by eZuce: None
Line 56: Line 54:
 * Remote participants by eZuce: Miyoki ==== Report of work (*:responsible person) ====
 * VAC: *Kimura
  * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
Line 58: Line 58:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Enomoto
   * Photo sensor noise was improved on Thursday and checked on Friday. We confirmed the noise becomes better.
   * Sampling model of RT model was changed from 16kHz to 2kHz to reduce 10min period glitch.
 * ETMX: *Hasegawa
  * Damping for yaw woks somehow and RMS is ~0.2urad.
  * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
 * ETMY: :Miyamoto, Shishido
  * No progress for damping.
 * ETMY: *Okutomi
  * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
Line 63: Line 66:
  * Camera: Inoue, Haino, Yokozawa, Cory, Binhua
   * ETMY Camera was broken by taking too many photos. Camera will be replaced.
   * ITMY camera is being set to look at BS.
   * BS PD will be replaced by Yokozawa.

  * IOO: Kitazawa, kokeyama
   * IO chassis will be replaced and being prepared.

  * CRY: mirror temperature ~110K.
   * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified.
 * DGS: *Yamamoto
  * IO chassis of k1ioo was disconnected somehow.
Line 75: Line 70:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Ushiba
   * Check the glitch with the 2kHz model.
   * Original REFL port will be tested to pick up Mich signal.

 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.

 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs

  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
Line 101: Line 72:
 * Issues
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
==== Work plan (*:responsible person) ====

 * IFO: Enomoto, Nakano
  * Damping, BS L2P, restoring alignment.

 * VAC: *Kimura
  * Identifies the location of leak.

 * VAC: *Inoue
  * Vacuum gage for wide area will be installed.


==== Laser hazard ====
 * [AM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [PM]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * [night]
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F


==== Weekly ====

 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.

 * week of 4/23
  * Operation

==== Issues ====

  * Large leak was found but it is not identified where it is.
  * IO chassis of k1ioo was disconnected somehow.
  * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
  * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
Line 109: Line 120:
==== Weekly meeting ==== === Weekly meeting ===
Line 114: Line 125:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 137: Line 154:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/17(Tue.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • VAC: *Kimura
    • Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
  • ETMX: *Hasegawa
    • Damping for yaw woks somehow and RMS is ~0.2urad.
    • A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
  • ETMY: :Miyamoto, Shishido
    • No progress for damping.
  • ETMY: *Okutomi
    • ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
  • DGS: *Yamamoto
    • IO chassis of k1ioo was disconnected somehow.

Work plan (*:responsible person)

  • IFO: Enomoto, Nakano
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Identifies the location of leak.
  • VAC: *Inoue
    • Vacuum gage for wide area will be installed.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

  • Large leak was found but it is not identified where it is.
  • IO chassis of k1ioo was disconnected somehow.
  • A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
  • ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)