Deletions are marked like this. | Additions are marked like this. |
Line 54: | Line 54: |
2017/2/27(Tue.) | 2017/2/28(Wed.) |
Line 59: | Line 59: |
* Alignment and ETMY: *Enomoto, Ushiba, Yamamoto * Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area. * Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared! |
* Alignment and ETMY: *Enomoto, Ushiba, Miyamoto * Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm. * Damping of pitch is still under investigation. TFs of pitch role etc. are dirty. |
Line 64: | Line 65: |
* IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still. | * A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one. * It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis. |
Line 66: | Line 68: |
* CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
* CRY: mirror temperature ~100K. |
Line 71: | Line 72: |
* ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
|
Line 75: | Line 73: |
* Camera: Yokozawa * fine tuning and safety. |
* Camera: Yokozawa * BS figure will be checked if no laser was coming. |
Line 78: | Line 76: |
* Height change of PRs: * It will be planed tomorrow. Preparation is almost done. |
* Height change of PRs: * Height of PR2 and PR2 will be lowered today. |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/26 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Enomoto
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/28(Wed.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
- Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm.
- Damping of pitch is still under investigation. TFs of pitch role etc. are dirty.
- IOO: kokeyama
- A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one.
- It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis.
- CRY: mirror temperature ~100K.
- Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
- Work plan (*:responsible person)
- Camera: Yokozawa
- BS figure will be checked if no laser was coming.
- Height change of PRs:
- Height of PR2 and PR2 will be lowered today.
- Camera: Yokozawa
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/26
- ETMY tuninng.
- Beam alignment to REFL port.
- 2/28: Height change for PRs
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/26
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 4 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools