2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/2/27(Tue.) | 2017/3/15(Thur.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Izumi | * Remote participants by eZuce: None |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Enomoto, Ushiba, Yamamoto * Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area. * Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared! |
==== Report of work (*:responsible person) ==== |
Line 63: | Line 57: |
* IOO: kokeyama * IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still. |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Tuning of ETMY damping is still going on. * Beam alignment to both end and REFL port was confirmed the last night. * Beam is now being drifted to down slowly at PSL by ~100urad. * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software. * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least. |
Line 66: | Line 64: |
* CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
* BS: Top of the BS chamber was tightened but no big shift was not found. * AOS: IYC and IYA started pumping down. * ETMY: *Enomoto * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something. * CRY: Mirror reached at 18K. |
Line 70: | Line 74: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
==== Work plan (*:responsible person) ==== * Alignment: Enomonoto, Izumi * IMMT coil driver will be checked. * REFL camera has been placed and will be setup today. * VAC: Uchiyama * Duct connection. |
Line 76: | Line 84: |
* fine tuning and safety. | * Both door will be closed today. Pump down will be start today. |
Line 78: | Line 86: |
* Height change of PRs: * It will be planed tomorrow. Preparation is almost done. |
* AOS: IYC will be closed and start pump-down. |
Line 81: | Line 88: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | |
Line 83: | Line 89: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
==== Laser hazard ==== * [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
Line 89: | Line 94: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
==== Weekly ==== * week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. |
Line 93: | Line 100: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
Line 103: | Line 107: |
* Connection of PD signal to DAQ should be implemented this week or next week. |
|
Line 109: | Line 116: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 114: | Line 121: |
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 137: | Line 146: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/15(Thur.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
- Tuning of ETMY damping is still going on.
- Beam alignment to both end and REFL port was confirmed the last night.
- Beam is now being drifted to down slowly at PSL by ~100urad.
- One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
- When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
- BS: Top of the BS chamber was tightened but no big shift was not found.
- AOS: IYC and IYA started pumping down.
- ETMY: *Enomoto
- BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.
- CRY: Mirror reached at 18K.
Work plan (*:responsible person)
- Alignment: Enomonoto, Izumi
- IMMT coil driver will be checked.
- REFL camera has been placed and will be setup today.
- VAC: Uchiyama
- Duct connection.
- Camera: Yokozawa
- Both door will be closed today. Pump down will be start today.
- AOS: IYC will be closed and start pump-down.
Laser hazard
- [AM] IR: PSL, Green: off.
- [PM] IR: PSL, Green: off.
- [night] IR: all, Green: off
Weekly
- week of 3/12
- 3/14: meeting for pump-down check
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues
- Connection of PD signal to DAQ should be implemented this week or next week.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)