Differences between revisions 317 and 345 (spanning 28 versions)
Revision 317 as of 2018-02-27 09:24:55
Size: 9328
Comment:
Revision 345 as of 2018-03-15 09:32:12
Size: 10012
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 54: Line 51:
2017/2/27(Tue.) 2017/3/15(Thur.)
Line 56: Line 53:
 * Remote participants by eZuce: Izumi  * Remote participants by eZuce: None
Line 58: Line 55:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Enomoto, Ushiba, Yamamoto
   * Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area.
   * Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared!
==== Report of work (*:responsible person) ====
Line 63: Line 57:
  * IOO: kokeyama
   * IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still.
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Tuning of ETMY damping is still going on.
  * Beam alignment to both end and REFL port was confirmed the last night.
  * Beam is now being drifted to down slowly at PSL by ~100urad.
  * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
  * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
Line 66: Line 64:
  * CRY: mirror temperature ~110K.
   * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified.
 * BS: Top of the BS chamber was tightened but no big shift was not found.

 * AOS: IYC and IYA started pumping down.

 * ETMY: *Enomoto
  * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.

 * CRY: Mirror reached at 18K.
Line 70: Line 74:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Ushiba
   * Check the glitch with the 2kHz model.
   * Original REFL port will be tested to pick up Mich signal.
==== Work plan (*:responsible person) ====

 * Alignment: Enomonoto, Izumi
  * IMMT coil driver will be checked.
  * REFL camera has been placed and will be setup today.

 * VAC: Uchiyama
  * Duct connection.
Line 76: Line 84:
  * fine tuning and safety.   * Both door will be closed today. Pump down will be start today.
Line 78: Line 86:
 * Height change of PRs:
  * It will be planed tomorrow. Preparation is almost done.
 * AOS: IYC will be closed and start pump-down.
Line 81: Line 88:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 83: Line 89:
 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
==== Laser hazard ====
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
 * [night] IR: all, Green: off
Line 89: Line 94:
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
==== Weekly ====
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 93: Line 100:
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

 
* week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
Line 103: Line 107:
  * Connection of PD signal to DAQ should be implemented this week or next week.

Line 109: Line 116:
==== Weekly meeting ==== === Weekly meeting ===
Line 114: Line 121:
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 137: Line 146:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/13 updated KAGRA/Commissioning/Commissioning_schedule_20180313.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/15(Thur.)

  • Remote participants by eZuce: None

Report of work (*:responsible person)

  • Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
    • Tuning of ETMY damping is still going on.
    • Beam alignment to both end and REFL port was confirmed the last night.
    • Beam is now being drifted to down slowly at PSL by ~100urad.
    • One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software.
    • When the bottom screws was tightened, oplev showed the shift of IMMT1 at least.
  • BS: Top of the BS chamber was tightened but no big shift was not found.
  • AOS: IYC and IYA started pumping down.
  • ETMY: *Enomoto
    • BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something.
  • CRY: Mirror reached at 18K.

Work plan (*:responsible person)

  • Alignment: Enomonoto, Izumi
    • IMMT coil driver will be checked.
    • REFL camera has been placed and will be setup today.
  • VAC: Uchiyama
    • Duct connection.
  • Camera: Yokozawa
    • Both door will be closed today. Pump down will be start today.
  • AOS: IYC will be closed and start pump-down.

Laser hazard

  • [AM] IR: PSL, Green: off.
  • [PM] IR: PSL, Green: off.
  • [night] IR: all, Green: off

Weekly

  • week of 3/12
    • 3/14: meeting for pump-down check
    • TMS installation at ETMY.
    • Connecting ducts at the corner area.
  • week of 3/19
    • Vacuum test at at the corner area.
    • TMS alignment using green light at ETMY.
    • Beam alignment to REFL port.
  • Issues
    • Connection of PD signal to DAQ should be implemented this week or next week.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)