9328
Comment:
|
9826
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/2/27(Tue.) | 2017/3/20(Tue.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Izumi | * Remote participants by eZuce: None |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Enomoto, Ushiba, Yamamoto * Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area. * Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared! |
==== Report of work (*:responsible person) ==== |
Line 63: | Line 57: |
* IOO: kokeyama * IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still. |
* VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. |
Line 66: | Line 60: |
* CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
* Alignment: *Izumi * All alignment to REFL after pump down was verified. * Only ETMY was off position by ~100urad. * ETMY: *Miyamoto * Diagonal of sensors. Still going on. * BS: Eleonora, Izumi * Coil balance is going on. * IMC: * "sleep" commands were removed from Guardian. * Cal: Yokozawa * We checked all the IMC TFs. |
Line 70: | Line 77: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
|
Line 75: | Line 78: |
* Camera: Yokozawa * fine tuning and safety. |
==== Work plan (*:responsible person) ==== |
Line 78: | Line 80: |
* Height change of PRs: * It will be planed tomorrow. Preparation is almost done. |
* Alignment, ETMY: *Izumi |
Line 81: | Line 82: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. * Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs * week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* Cal: Yokozawa * Injection will be tested soon. |
Line 102: | Line 86: |
==== Laser hazard ==== * [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. ==== Weekly ==== * week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa * week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
|
Line 103: | Line 104: |
Line 109: | Line 111: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 114: | Line 116: |
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 137: | Line 142: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/20(Tue.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- PR2 assembly frames will be removed soon.
- Alignment: *Izumi
- All alignment to REFL after pump down was verified.
- Only ETMY was off position by ~100urad.
- All alignment to REFL after pump down was verified.
- ETMY: *Miyamoto
- Diagonal of sensors. Still going on.
- BS: Eleonora, Izumi
- Coil balance is going on.
- IMC:
- "sleep" commands were removed from Guardian.
- Cal: Yokozawa
- We checked all the IMC TFs.
Work plan (*:responsible person)
- Alignment, ETMY: *Izumi
- Cal: Yokozawa
- Injection will be tested soon.
Laser hazard
- [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
- [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
Weekly
- week of 3/19
- TMS alignment using green light at ETMY.
- 3/21: Calibration test using MC.
- 3/23: door between EXA and EXC will be removed.
- EX PD will be removed at the same time.: *Yokozawa
- week of 3/26
- Rough alignment of ETMX will be planed using IR.
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools