Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 54: Line 51:
2017/2/27(Tue.) 2017/3/26(Mon.)
Line 56: Line 53:
 * Remote participants by eZuce: Izumi  * Remote participants by eZuce: Shoda
Line 58: Line 55:
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Enomoto, Ushiba, Yamamoto
   * Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area.
   * Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared!
==== Report of work (*:responsible person) ====
Line 63: Line 57:
  * IOO: kokeyama
   * IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still.
 * ETMY: *Miyamoto
  * Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close!
Line 66: Line 60:
  * CRY: mirror temperature ~110K.
   * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified.
 * BS: *Eleonora, Yamamoto
  * DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently.

 * Camera: *Inoue
  * X end camera was recovered, needs PC tuning.

 * Camera: Yokozawa, Yamamoto, Miyamoto
  * X end camera will be recovered.
  * IYC cooling started.
Line 70: Line 71:
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Ushiba
   * Check the glitch with the 2kHz model.
   * Original REFL port will be tested to pick up Mich signal.
==== Work plan (*:responsible person) ====
Line 75: Line 73:
 * Camera: Yokozawa
  * fine tuning and safety.
 * BS: *Enomonot
  * Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week.
Line 78: Line 76:
 * Height change of PRs:
  * It will be planed tomorrow. Preparation is almost done.
 * AOS: *Akutsu, Yokogawa
  * BRT alignment is still going on.
  * Oplev work at EXC. It will be available early this week.
Line 81: Line 80:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 83: Line 81:
 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
==== Laser hazard ====
 * [AM]
  * IR: PSL
  * Green: none
 * [PM]
  * IR: PSL
  * Green: none
Line 89: Line 89:
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
 * [night]
  * IR: PSL
  * Green: none
Line 93: Line 93:
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.
==== Weekly ====
Line 97: Line 95:
  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.

 * week of 3/26
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * EX PD will be removed.: *Yokozawa
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.

 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.

 * week of 4/9
Line 103: Line 110:
Line 109: Line 117:
==== Weekly meeting ==== === Weekly meeting ===
Line 114: Line 122:
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 137: Line 149:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/26(Mon.)

  • Remote participants by eZuce: Shoda

Report of work (*:responsible person)

  • ETMY: *Miyamoto
    • Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close!
  • BS: *Eleonora, Yamamoto
    • DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently.
  • Camera: *Inoue
    • X end camera was recovered, needs PC tuning.
  • Camera: Yokozawa, Yamamoto, Miyamoto
    • X end camera will be recovered.
    • IYC cooling started.

Work plan (*:responsible person)

  • BS: *Enomonot
    • Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week.
  • AOS: *Akutsu, Yokogawa
    • BRT alignment is still going on.
    • Oplev work at EXC. It will be available early this week.

Laser hazard

  • [AM]
    • IR: PSL
    • Green: none
  • [PM]
    • IR: PSL
    • Green: none
  • [night]
    • IR: PSL
    • Green: none

Weekly

  • week of 3/26
    • Connection of cable at ETMX and starting control.
    • Rough alignment of ETMX using IR.
      • EX PD will be removed.: *Yokozawa
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
  • week of 4/9
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)