Line 11: | Line 11: |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/2/27(Tue.) | 2017/3/29(Thur.) |
Line 56: | Line 53: |
* Remote participants by eZuce: Izumi | * Remote participants by eZuce: None |
Line 58: | Line 55: |
* Report of work (*:responsible person) * Alignment and ETMY: *Enomoto, Ushiba, Yamamoto * Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area. * Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared! |
==== Report of work (*:responsible person) ==== |
Line 63: | Line 57: |
* IOO: kokeyama * IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still. |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Jump of GAS filter was compensated and fixed. * Yaw was roughly aligned by top filter. * First contact was removed. * Top chamber was closed. * Beam reached at the ETMX. * Baffle PD was tested well. |
Line 66: | Line 65: |
* CRY: mirror temperature ~110K. * The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified. |
* BS: *Enomoto * We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch. * BRT: Akutsu * Light is collimated well. * Camera: Yokozawa * EX camera takes every one hour. * Needs 1 sec picture in the weekend. ==== Work plan (*:responsible person) ==== * ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Mirror will be aligned with beam today. * CAL: *Yamamoto * CAL model is tested using iMC. |
Line 70: | Line 84: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Ushiba * Check the glitch with the 2kHz model. * Original REFL port will be tested to pick up Mich signal. |
==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 75: | Line 92: |
* Camera: Yokozawa * fine tuning and safety. |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 78: | Line 96: |
* Height change of PRs: * It will be planed tomorrow. Preparation is almost done. |
==== Weekly ==== |
Line 81: | Line 98: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. | * week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
Line 83: | Line 104: |
* Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
Line 89: | Line 108: |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber |
* week of 4/9 * Closing EXC |
Line 93: | Line 111: |
* week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
==== Issues ==== |
Line 97: | Line 113: |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* BS: DAC had some glitches with no output (even dac kill and master SW are off). |
Line 101: | Line 115: |
* Issues |
|
Line 109: | Line 121: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 114: | Line 126: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 137: | Line 153: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/29(Thur.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Jump of GAS filter was compensated and fixed.
- Yaw was roughly aligned by top filter.
- First contact was removed.
- Top chamber was closed.
- Beam reached at the ETMX.
- Baffle PD was tested well.
- BS: *Enomoto
- We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch.
- BRT: Akutsu
- Light is collimated well.
- Camera: Yokozawa
- EX camera takes every one hour.
- Needs 1 sec picture in the weekend.
Work plan (*:responsible person)
- ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
- Mirror will be aligned with beam today.
- CAL: *Yamamoto
- CAL model is tested using iMC.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Closing EXC
Issues
- BS: DAC had some glitches with no output (even dac kill and master SW are off).
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents