Line 54: Line 54:
2017/3/1(Thur.) 2017/3/2(Fri.)
Line 60: Line 60:
  * Height change of PRs: Aso, Takahashi, Ohishi, Miyo
   * We opend the chamber and we confirmed that the height of PR2 and PR3 were not at the wrong point.
   * LVDT had jump several times in the past, so absolute position of LVDT is not trustable.
   * It means that the beam changed upstream PR like IMMT, or MC.
  * Alignment: Enomoto, Miyo, Yokozawa
   * IMC and IMMT was aligned to center PRs.
   * Beam spot was not seen at the end.
Line 66: Line 65:
  * Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
   * Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm.
   * Damping of pitch is still under investigation. TFs of pitch role etc. are dirty.
  * IOO: kokeyama
   * Alignment to MC was fixe.
Line 70: Line 68:
  * AOS:
   * Lasers of oplev will can be dying soon.
    * The lifetime is about 100000h.
Line 71: Line 72:
  * IOO: kokeyama
   * A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one.
   * It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis.

  * CRY: mirror temperature ~100K.
  * CRY: mirror temperature 89K.
Line 80: Line 77:
  * Camera: Yokozawa
   * BS figure will be checked if no laser was coming.
  * Alignment:
   * Alignment to IYA, or IYC will be checked and we will find the spot at the end then.
Line 90: Line 86:
   * 2/28: Height change for PRs

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/26 updated KAGRA/Commissioning/Commissioning_schedule_20180227.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Enomoto



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/2(Fri.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment: Enomoto, Miyo, Yokozawa
      • IMC and IMMT was aligned to center PRs.
      • Beam spot was not seen at the end.
      • We absolutely need monitors to check beam position at all the mirrors.
    • IOO: kokeyama
      • Alignment to MC was fixe.
    • AOS:
      • Lasers of oplev will can be dying soon.
        • The lifetime is about 100000h.
    • CRY: mirror temperature 89K.
  • Work plan (*:responsible person)
    • Alignment:
      • Alignment to IYA, or IYC will be checked and we will find the spot at the end then.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/26
      • ETMY tuninng.
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 5 >  >>
Mon Tue Wed Thu Fri Sat Sun
    1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31    


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)