Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/3/13 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 54: Line 51:
2017/3/1(Thur.) 2017/3/12(Wed.)
Line 58: Line 55:
 * Report of work (*:responsible person) ==== Report of work (*:responsible person) ====
Line 60: Line 57:
  * Height change of PRs: Aso, Takahashi, Ohishi, Miyo
   * We opend the chamber and we confirmed that the height of PR2 and PR3 were not at the wrong point.
   * LVDT had jump several times in the past, so absolute position of LVDT is not trustable.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
  * Tuning of ETMY damping is still going on.
  * Alignment to end was checked last.
Line 66: Line 61:
  * Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
   * Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm.
   * Damping of pitch is still under investigation. TFs of pitch role etc. are dirty.
 * BS: Top of the BS chamber is opened now for the work of duct connection.
Line 71: Line 64:
  * IOO: kokeyama
   * A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one.
   * It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis.
 * Camera: Yokozawa
  * IXA camera alignment was done.
Line 75: Line 67:
  * CRY: mirror temperature ~100K.  * IMMT: Kokeyama
  * Cable was cut, probably by work of duct connection.

 * CRY: Mirror reached at 18K.
Line 78: Line 73:
 * Work plan (*:responsible person) ==== Work plan (*:responsible person) ====
Line 80: Line 75:
  * Camera: Yokozawa
   * BS figure will be checked if no laser was coming.
 * Alignment: Enomonoto, Izumi
  * IMMT coil driver will be checked.
  * REFL camera has been placed and will be setup today.

 * VAC: Uchiyama
  * Duct connection.

 * Camera: Yokozawa
  * Both door will be closed today. Pump down will be start today.

 * AOS: IYC will be closed and start pump-down.
Line 84: Line 88:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. ==== Laser hazard ====
 * [AM] IR: PSL, Green: off.
 * [PM] IR: PSL, Green: off.
Line 86: Line 92:
 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
Line 92: Line 93:
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
==== Weekly ====
 * week of 3/12
  * 3/14: meeting for pump-down check
  * TMS installation at ETMY.
  * Connecting ducts at the corner area.
Line 96: Line 99:
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

 
* week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
 * week of 3/19
  * Vacuum test at at the corner area.
  * TMS alignment using green light at ETMY.
  * Beam alignment to REFL port.
Line 106: Line 106:
  * Connection of PD signal to DAQ should be implemented this week or next week.

Line 112: Line 115:
==== Weekly meeting ==== === Weekly meeting ===
Line 117: Line 120:
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/13 updated KAGRA/Commissioning/Commissioning_schedule_20180313.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/12(Wed.)

  • Remote participants by eZuce: None

Report of work (*:responsible person)

  • Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
    • Tuning of ETMY damping is still going on.
    • Alignment to end was checked last.
  • BS: Top of the BS chamber is opened now for the work of duct connection.
  • Camera: Yokozawa
    • IXA camera alignment was done.
  • IMMT: Kokeyama
    • Cable was cut, probably by work of duct connection.
  • CRY: Mirror reached at 18K.

Work plan (*:responsible person)

  • Alignment: Enomonoto, Izumi
    • IMMT coil driver will be checked.
    • REFL camera has been placed and will be setup today.
  • VAC: Uchiyama
    • Duct connection.
  • Camera: Yokozawa
    • Both door will be closed today. Pump down will be start today.
  • AOS: IYC will be closed and start pump-down.

Laser hazard

  • [AM] IR: PSL, Green: off.
  • [PM] IR: PSL, Green: off.

Weekly

  • week of 3/12
    • 3/14: meeting for pump-down check
    • TMS installation at ETMY.
    • Connecting ducts at the corner area.
  • week of 3/19
    • Vacuum test at at the corner area.
    • TMS alignment using green light at ETMY.
    • Beam alignment to REFL port.
  • Issues
    • Connection of PD signal to DAQ should be implemented this week or next week.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)