Line 11: | Line 11: |
2017/2/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}} |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
Line 18: | Line 18: |
* Beam leading to REFP port * *Enomoto |
|
Line 54: | Line 51: |
2017/3/1(Thur.) | 2017/3/16(Fri.) |
Line 58: | Line 55: |
* Report of work (*:responsible person) | ==== Report of work (*:responsible person) ==== |
Line 60: | Line 57: |
* Height change of PRs: Aso, Takahashi, Ohishi, Miyo * We opend the chamber and we confirmed that the height of PR2 and PR3 were not at the wrong point. * LVDT had jump several times in the past, so absolute position of LVDT is not trustable. * It means that the beam changed upstream PR like IMMT, or MC. * We absolutely need monitors to check beam position at all the mirrors. |
* VAC: *Uchiyama, Kimura, Suzuki * Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today. |
Line 66: | Line 60: |
* Alignment and ETMY: *Enomoto, Ushiba, Miyamoto * Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm. * Damping of pitch is still under investigation. TFs of pitch role etc. are dirty. |
* Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Yaw damping stared working by changing polarity. * Beam alignment to both end and REFL port was confirmed the last night. * ~10rad shift was seen as usual. * Clipping was fixed by PSL alignment yesterday. * PR3 is being shifted to yaw by pump down by ~300urad. * LSC model as full model started running at k1imc0. Dolhpin will be conected soon. * Camera: Yokozawa * IYAC and IXAC areas are being pumped down. * CRY: Mirror reached at 18K. |
Line 71: | Line 74: |
* IOO: kokeyama * A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one. * It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis. |
|
Line 75: | Line 75: |
* CRY: mirror temperature ~100K. | ==== Work plan (*:responsible person) ==== * VAC: Uchiyama * Pump down. * DGS: *Miyakawa * 10GB network card at dc0 will be replaced. |
Line 78: | Line 84: |
* Work plan (*:responsible person) | ==== Laser hazard ==== * [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off |
Line 80: | Line 89: |
* Camera: Yokozawa * BS figure will be checked if no laser was coming. |
==== Weekly ==== * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. |
Line 83: | Line 94: |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. * Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * 2/28: Height change for PRs * week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
* week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. |
Line 106: | Line 101: |
* Connection of PD signal to DAQ should be implemented this week or next week. |
|
Line 112: | Line 110: |
==== Weekly meeting ==== | === Weekly meeting === |
Line 117: | Line 115: |
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || |
|
Line 140: | Line 140: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/13 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/16(Fri.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama, Kimura, Suzuki
- Pump down started yesterday, but a big leak was found. We changed a flange at BS and it is ready to pump down again today.
- Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi
- Yaw damping stared working by changing polarity.
- Beam alignment to both end and REFL port was confirmed the last night.
- ~10rad shift was seen as usual.
- Clipping was fixed by PSL alignment yesterday.
- PR3 is being shifted to yaw by pump down by ~300urad.
- LSC model as full model started running at k1imc0. Dolhpin will be conected soon.
- Camera: Yokozawa
- IYAC and IXAC areas are being pumped down.
- CRY: Mirror reached at 18K.
Work plan (*:responsible person)
- VAC: Uchiyama
- Pump down.
- DGS: *Miyakawa
- 10GB network card at dc0 will be replaced.
Laser hazard
- [AM] IR: PSL, Green: off.
- [PM] IR: PSL, Green: off.
- [night] IR: all, Green: off
Weekly
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Beam alignment to REFL port.
- Issues
- Connection of PD signal to DAQ should be implemented this week or next week.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools