Differences between revisions 319 and 353 (spanning 34 versions)
Revision 319 as of 2018-03-01 08:59:47
Size: 9420
Comment:
Revision 353 as of 2018-03-22 09:30:44
Size: 10272
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/2/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180227.png||width=1200}}
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
Line 18: Line 18:

 * Beam leading to REFP port
  * *Enomoto
Line 54: Line 51:
2017/3/1(Thur.) 2017/3/21(Thur.)
Line 56: Line 53:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Kimura, Miyoki
Line 58: Line 55:
 * Report of work (*:responsible person) ==== Report of work (*:responsible person) ====
Line 60: Line 57:
  * Height change of PRs: Aso, Takahashi, Ohishi, Miyo
   * We opend the chamber and we confirmed that the height of PR2 and PR3 were not at the wrong point.
   * LVDT had jump several times in the past, so absolute position of LVDT is not trustable.
   * It means that the beam changed upstream PR like IMMT, or MC.
   * We absolutely need monitors to check beam position at all the mirrors.
 * IFO: *Izumi, Miyamoto, Eleonora
  * Daily Beam check was confirmed at the REFL port yesterday evening.
  * Measurement of BS sensing and driving matrix and diagonalizarion of them.
   * This method should be automatically performed, but still we needs some work to be done.
  * T of ETMY was checked and improved. We need the same work for L.
  * LSC screen has been updated.
Line 66: Line 64:
  * Alignment and ETMY: *Enomoto, Ushiba, Miyamoto
   * Beam shift at the PR2 was large ~1cm, and the beam was clipped at the PR3 ~10cm.
   * Damping of pitch is still under investigation. TFs of pitch role etc. are dirty.
  * AOS: *Akutsu, Yokogawa
   * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
Line 71: Line 68:
  * IOO: kokeyama
   * A good IO chassis which showed the correct IRIG-B ~12 was found. We will replace the current one to the new good one.
   * It was noticed that MC and FSS shows something wrong this morning. We will check it before changing IO chassis.

  * CRY: mirror temperature ~100K.
 * IMC, CAL: Yokozawa, Yamamoto
  * IMC Transmitted light is too low. Alignment should be checked.
  * Injection to MCE for calibration was tested.
  
 * VAC: Uchiyama
  * Vacuum level of X arm is degraded.
Line 78: Line 76:
 * Work plan (*:responsible person) ==== Work plan (*:responsible person) ====
Line 80: Line 78:
  * Camera: Yokozawa
   * BS figure will be checked if no laser was coming.
 * Alignment: *Izumi
  * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
   * Needs power supply for QPD.

 * AOS: *Akutsu, Yokogawa
  * TMS alignment at ETMY.
  * Cooling will start at 10AM.
Line 84: Line 87:
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. ==== Laser hazard ====
 * [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
 * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.
Line 86: Line 92:
 * Weekly
  * Week of 2/26
   * ETMY tuninng.
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
==== Weekly ====
Line 92: Line 94:
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
 * week of 3/19
  * TMS alignment using green light at ETMY.
  * 3/21~: Calibration test using MC.
  * 3/23: door between EXA and EXC will be removed.
   * EX PD will be removed at the same time.: *Yokozawa
Line 96: Line 100:
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
 * week of 3/26
  * Rough alignment of ETMX will be planed using IR.
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
Line 106: Line 105:
Line 112: Line 112:
==== Weekly meeting ==== === Weekly meeting ===
Line 117: Line 117:
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
Line 140: Line 143:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/20 updated KAGRA/Commissioning/Commissioning_schedule_20180320.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/3/21(Thur.)

  • Remote participants by eZuce: Kimura, Miyoki

Report of work (*:responsible person)

  • IFO: *Izumi, Miyamoto, Eleonora
    • Daily Beam check was confirmed at the REFL port yesterday evening.
    • Measurement of BS sensing and driving matrix and diagonalizarion of them.
      • This method should be automatically performed, but still we needs some work to be done.
    • T of ETMY was checked and improved. We need the same work for L.
    • LSC screen has been updated.
    • AOS: *Akutsu, Yokogawa
      • Green light reached to ETMY on Tuesday. Misalignment was ~100urad order.
  • IMC, CAL: Yokozawa, Yamamoto
    • IMC Transmitted light is too low. Alignment should be checked.
    • Injection to MCE for calibration was tested.
  • VAC: Uchiyama
    • Vacuum level of X arm is degraded.

Work plan (*:responsible person)

  • Alignment: *Izumi
    • ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX.
      • Needs power supply for QPD.
  • AOS: *Akutsu, Yokogawa
    • TMS alignment at ETMY.
    • Cooling will start at 10AM.

Laser hazard

  • [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F.
  • [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F.

Weekly

  • week of 3/19
    • TMS alignment using green light at ETMY.
    • 3/21~: Calibration test using MC.
    • 3/23: door between EXA and EXC will be removed.
      • EX PD will be removed at the same time.: *Yokozawa
  • week of 3/26
    • Rough alignment of ETMX will be planed using IR.
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)